Dale Rosinski stands on the finished side of a 1,500-foot curved bridge across the valley above Fort Cherry Road in Robinson, Washington County. He watches as crews set reinforcement bars on the unfinished bridge beside it in preparation for overnight paving.

Miles of finished roadway for the new Southern Beltway lead up to each end of the bridge. In some areas, mile markers and exit signs already are in place.

“It’s really starting to come together,” said Mr. Rosinksi, construction project manager for consultant CDR Maguire.

The 13-mile, $900 million toll road that the Pennsylvania Turnpike is building near Pittsburgh International Airport — joining Interstate 79 near Southpointe with Route 22 — is heading into its final year of mainline construction.

Advertise with us

Although some excavation remains for the complicated I-79 interchange, four years of work to level hills and fill in valleys for road construction has been completed. Five of the seven sections of the project are just waiting finishing touches.

The Southern Beltway is starting to look like the first totally new highway built in this region in decades.

Bridging a challenge

It’s hard to surprise Bob Kohlmyer, a construction supervisor for CDR Maguire with decades of construction experience.

But when he walked into a meeting with contractors for the bridge over Fort Cherry Road earlier this year, he didn’t expect their solution to an age-old challenge. When crews assemble girders for the framework of a new bridge, it’s almost inevitable that the beams come up at least a few inches short because bolts fit in a loose slot that allows some variation from one to the next.

Advertise with us

In Mr. Kohlmyer’s experience, crews usually make adjustments to the beams to make everything fit. Not in this case.

Instead, when crews came up short on the fourth of seven piers, they attached hydraulic jacks to the top of the 115-foot-tall bridge pier to pull it closer to the beams. Of course, this is after the piers had been anchored in bedrock at least 10 feet under ground.

“This is the first one where I’ve seen them do that,” Mr. Kohlmyer said. “But it worked. There’s enough play in the pier that they could move it without causing any problem.”

Just building a curved bridge comes with its own challenges.

For example, beams for curved bridges usually are assembled in pairs on the ground. That’s because experience has taught workers that beams installed one at a time twist inexplicably and quickly throw the structure way off kilter, but that doesn’t happen with pairs.

Advertise with us

Once the pairs were assembled on the ground, a precisely positioned crane lifted them — in this case more than 100 feet — into place. Engineers spend hours calculating within inches the position of the crane and the precise lift point on the beams because being slightly wrong could cause the crane to tip or otherwise not position the beam properly.

As Mr. Rosinksi put it, the process involves material that is “very large, very heavy with little room for error.”

On a long bridge like this, pouring concrete for the deck also takes some engineering finesse. Using a 40-foot-wide slipform paving machine, crews poured the area between bridge piers first to take the camber out of the surface, then did the area over the piers.

If they did the piers first, the middle areas would develop even more camber and make the road hard to drive.

The Post-Gazette takes a look at the enormous effort that goes into building the next segment of the Southern Beltway.
Click here to read more.

Advertise with us

In addition, the curves have a slight bank like a race track to help hold vehicles onto the surface. That bank is obvious walking across the pavement, but Mr. Rosinski said it will be barely noticeable to drivers.

The fact that the bridge crosses over three trails, two roads and a stream also required close communication with people who want to use those facilities during construction.

“It’s challenging, but it’s construction,” said Josh Farley, assistant project manager for Maguire. “It’s just the job we do in a lot of ways.”

Interchange breakthrough

Crews for Walsh Construction II had a major breakthrough last month after building the southbound bridge on I-79 just north of the Southpointe exit: They excavated away about 30 feet of land just below the surface of the structure, opening space under it so it actually has something to “bridge.”

Advertise with us

That open space is the key to the beltway’s interchange with I-79, the most expensive, most complicated section of the project at $174.3 million. The new valley will accommodate the spaghetti-like series of ramps that will go under the highway before connecting the new toll road with the interstate.

Last summer, crews closed the southbound lanes in that area and shifted all traffic to the northbound side. That allowed them to build the first bridge.

But they built that bridge by excavating just enough space for the middle pier and the abutments on each end of the 430-foot span. Dirt remained under the rest of the bridge.

After the bridge was finished and all traffic shifted to the southbound side, excavators finished opening up the valley by clearing dirt about 30 feet deep from each side of the pier and creating temporary roads where the ramps will be in the future.

On Thursday, Mr. Farley watched from the old, abandoned northbound lanes that sit about 10 feet lower than the southbound lanes as three excavators filled dump trucks in the new valley.

Advertise with us

Views of the Southern Beltway project

Although four lanes of traffic on the southbound side have been jammed into the space that usually carries two lanes and part of the median, motorists whizzed by. The narrow lanes haven’t created any problems with congestion during the project.

“People are driving too fast, which means [the conditions] are too good,” Mr. Farley said.

The crews are preparing the site to raise the northbound lanes so the new bridge will be parallel with the southbound side and to narrow the median in this area from 40 feet to 15 feet. This bridge will be built in a more traditional manner above the open valley.

In addition, a 40-foot hill in the distance between the northbound lanes and Morganza Road will be excavated for one of the interchange ramps. For now, the space under the bridge will serve as the service road for a parade of dump trucks hauling dirt from one side of the interstate to the other.

“We’ve got about two million cubic yards of material on the east side of I-79 that’s going over to the west side of I-79,” Mr. Farley said.  “We’ve got plenty of dirt to go around.”

Advertise with us

That’s what’s left of the 6.5 million cubic yards of dirt that crews will move as part of the interchange project. Engineers use computer modeling to determine where to use the material elsewhere because “keeping it on site is cost effective” compared to hauling it away and dumping it.

On the west side of the interstate, crews are running a crew of five dump trucks from the on-site concrete plant to the mainline just down the hill, where a crew of about a dozen use a slipform paving machine to lay fresh pavement. In this digital age, a series of surveying machines send radio signals to the machine to control the thickness of the pour, a process done in the past using lines of string.

Crews use squeegees on 20-foot poles to smooth the surface and eliminate any imperfections. Another machine follows the paver to spray a special compound on the surface to keep it from curing too quickly, which causes more cracks.

The goal is to pave the mainline to the edge of the bridge and leave the path under open so it can be used for moving dirt, and then pave as much of the interchange ramps on the east side as possible before the snow flies.

“The big focus for the winter months is hauling the material from the east side so that is ready for paving next year,” Mr. Farley said. “As soon as humanly possible next spring, we’ll start paving again and keep moving through the season until we’re done.”

Advertise with us

Home stretch

Last year, with activity in each section of the project, crews were performing about $1 million of work every day on the beltway. Now, entering the sprint to open the mainline next fall, that’s down to about $500,000 a day.

In addition to the paving, remaining work for next year includes marking lanes and installing millions of dollars worth of electronic message boards and traditional road signs.

The goal, despite two summers of near-record rain and a three-week stoppage in March due to the COVID-19 pandemic, remains to finish work on the I-79 interchange by June 2022.

“This [dry, hot summer] hasn’t been the best of weather for a lot of industries, but for us it was just what we needed,” Mr.  Farley said. “We’re back on schedule and should be finished by June 2022.”

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.