Crews finished moving the second span of the Shaler Street bridge into place just after 4 p.m. Tuesday above Route 19/51 near the West End Bridge.
For the first time in Pennsylvania, the state Department of Transportation had Swank Construction Co. assemble the spans for the new bridge in a parking lot beside the highway. Subcontractor Mammoet, a Dutch-based firm, used a series of small hydraulic trailers to move the 70-foot-long, 270-ton spans into place.
“They just set it down a few minutes ago,” PennDOT spokesman Steve Cowan said about 4:30 p.m. “Everything is good. They just eased the trailers away and everything is good to go.”
The first span was placed on Monday.
_____________
VIDEO: Watch footage from Monday, when crews worked to put the first span of the Shaler Street bridge in place:
PennDOT replaces Shaler St. Bridge over Route 19/51
(Video by Andrew Rush/Post-Gazette)
_____________
The highway has been closed since Sunday so crews could build a temporary road to move the spans about 1,000 feet down the road and, in the case of the first span that passes above the northbound lanes, across the highway. The second span rests above the southbound lanes so it had to be moved a shorter distance.
Mr. Cowan said workers ran into no unexpected problems setting the second span. Crews finished clearing the temporary road Tuesday night and the highway was expected to reopen at 6 a.m. Wednesday with one lane of traffic in each direction.
PennDOT used the special construction process on Shaler Street to reduce the amount of time the bridge and highway had to be closed. In this process, the bridge was closed since early September and the highway was closed for about seven days where regular construction would have required six to eight months for bridge replacement and resulted in many overnight and weekend highway closures.
The bridge should be open in two to three weeks once crews finish its surface and approaches at each end.
The bridge is part of a $14.3 million project to rebuild the highway and lower the exit ramp to the Parkway West by two to three feet to keep trucks from hitting another overhead bridge there.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.