PennDOT replaces Shaler St. Bridge over Route 19/51

The Pennsylvania Department of Transportation is finding that making history takes time.

The department had hoped to move two huge bridge spans Monday morning along Route 19/51 to replace the Shaler Street Bridge that passes above the highway. But by the end of daylight, crews had one of the spans in place and decided to wait until Tuesday to move the second one.

The project marks the first time in Pennsylvania that crews have assembled bridge spans off site and moved them into place, a process PennDOT says greatly reduces the time that the bridge has to be closed and traffic restricted on the highway beneath it.

In all, Monday’s move of a 70-foot-long, 270-ton span was part a feat of strength, part precision.

Advertise with us

Over the past few months, Swank Construction Co. assembled the spans in the Minnotte Manufacturing Co. parking lot alongside the highway. Shaler Street connects Mount Washington with Duquesne Heights.

The move itself was delayed until after 1 p.m. while crews built a temporary road from the parking lot and across the median between the lanes of the highway. Workers placed and rolled about 2,500 tons of gravel for a moving path that served two purposes: It provided footing for the two trains of 12 hydraulic trailers each and raised the level of the road so the transporters could reach the tops of the pier and abutment where the span would be placed.

The installation of the road was measured using GPS coordinates so that it was within 1/10 of an inch of specifications, said Jason Zang, assistant district executive for construction for PennDOT’s District 11.

When the road was ready, subcontractor Mammoet, a Dutch-based company that specializes in lifting heavy objects, used a team of three to coordinate the move — a power-pack operator, a spotter and a project engineer. The trailers formed the stems of an H and lifted the span on special plates that had been installed beneath it.

The trailers moved at a walking pace from the parking lot within inches of a Minnotte building, down the southbound lanes of the highway past the site of the bridge, then across the median to the northbound lanes, which were 13 inches higher at that point.

Advertise with us

Observers about 50 yards away were struck by how quiet the move was — the only sound came from a drone recording the activity from above.

As the trailers moved, each of their hydraulic axles adjusted to the differences in the surface, often automatically but sometimes on instruction from the spotter, who was watching the bubble of an 8-foot-long level on the span. The key was to keep the span as level as possible.

From there, Mammoet project engineer Patrick Heer estimated it would take less than 15 minutes moving in reverse to reach the site and lay the span in place from Mount Washington on the upper end to the pier in the median. But once the trailers reached the site, crews had to make adjustments to the temporary road surface to improve its stability, delaying placement of the beam for about 90 minutes.

After the span was in place, it took almost two more hours before the trailers were eased away.

“It’s pretty typical of placing a bridge that you have to make some adjustments,” said Mr. Heer, who has been involved in about a half-dozen bridge placements in his four years with the company. It often involves “a little finesse” to get a huge, pre-built piece into its final location, he said.

Advertise with us

Cheryl Moon-Sirianni, PennDOT’s District 11 executive, said this process is more expensive than typical construction and is beneficial only when it can greatly reduce the time a road is out of service or has traffic disrupted. In this case, the bridge has been closed since early September, but the highway beneath it will only be closed for a total of seven days. Normal construction methods would have closed the bridge for six to eight months and required extensive nighttime and weekend highway closures.

Crews were expected to move the second span into place early Tuesday. That should be an easier process since the trailers don’t have to cross the median.

Route 19/51 should reopen Wednesday morning and the new bridge should be open in two to three weeks, after crews finish work on the approaches.

Swank’s $14.3 million contract includes rebuilding the highway surface and lowering the road two to three feet near the ramp to the Parkway West so trucks quit hitting an overhead bridge there.

Mr. Heer said he enjoyed getting out of his New Jersey office to watch engineering calculations in action.

Advertise with us

“It’s something special to watch it executed,” he said. “How often do you get to see something so big move so easily? The coolest thing is, we get to change the horizon.”

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.