The Pennsylvania Department of Transportation’s new schedule for replacing the Shaler Street Bridge calls for traffic restrictions on Route 19/51 near the West End Bridge beginning Sunday afternoon and lasting until Wednesday morning.
For the first time in Pennsylvania, PennDOT built two spans for the replacement bridge in a parking lot alongside the highway and will use special hydraulic trailers to move it across and above the highway. The bridge sits at an angle and connects Mount Washington on the high side with Duquesne Heights on the low side.
The northbound highway will close from the Parkway West to the West End Circle at 2 p.m. Sunday and the southbound lanes will close at 7 p.m. Sunday so crews can prepare the road surface. Dutch-based Mammoet is expected to begin moving two 70-foot-long, 270-ton bridge spans Monday morning from the parking lot, down the highway and into place using two teams of 12 hydraulic trailers.
With this method, PennDOT said the bridge will be replaced within two months. With normal construction, the bridge would have been closed six to eight months and the highway would have had a series of weekend and overnight closures instead of about one week of closures, three days to demolish the old bridge and four to install the new one.
The project had been scheduled to begin Wednesday but was postponed due to rainy weather and high winds.