Construction continues on Route 51/Route 19 between the Interstate 376 interchange and West End Circle, where workers are replacing the road surface and building a new span to replace the Shaler Street Bridge.
Swank Construction Co., which is handling the $14.55 million contract, and its subcontractors are using two sections to build the new 140-foot long span.
Each 70-foot section of the replacement bridge was constructed in a parking lot at Minnotte Manufacturing Corp. near one end of the existing structure. Crews are now putting the sections into the place by using pre-built abutments.
Shaler Street begins at Woodville Avenue and runs above Route 51/19 to Grandview Avenue on Mount Washington.
Most of the construction will take place during daylight hours and one lane of traffic will be maintained in each direction for most of the project.
The project is expected to be completed in December.
Also on Route 51, but miles away in West Elizabeth, PennDOT announced that the circle ramp that brings northbound traffic onto the southbound lanes of the Elizabeth Bridge will close Wednesday.
The long-term closure will begin at 6 a.m. and continue through early September, PennDOT said. It’s part of a $31.3 million project to rehabilitate the bridge, which crosses the Monongahela River.
Here is the posted detour:
● Continue on northbound Route 51 passed the closed ramp
● Take the ramp to Ridge Road/Clairton
● Turn left onto Ridge Road
● Turn left onto the ramp to southbound Route 51
● End detour





Comments