Nizar Sandi looks out the window at crews working on the sidewalk in front of his Nick’s Imports and shakes his head. It’s barely six weeks into two years of construction projects along East Carson Street on Pittsburgh’s South Side, and Mr. Sandi feels lonely.
“I’ve lost about 70 percent of my foot traffic,” he said Wednesday as he sat in the business he’s run for 22 years. “In seven hours, I might have two customers. Basically, nobody is coming to the South Side any more.”
Last month, A. Merante Contracting Inc. began a $3 million project for the city that involves replacing a strip of sidewalk closest to the curb to add pedestrian lighting and hanging flower baskets from South 10th to South 17th streets and lights and 60 new trees from South 17th to South 25th streets. The plan was to break the project into a series of three-week segments so that no one area was under construction for an extended period.
But six weeks into the 24-week sidewalk project, that has changed substantially because crews found unexpected underground utility vaults in the first two weeks that will require more attention, Emily Gaspich, project coordinator for the city’s Department of Mobility and Infrastructure, said Thursday. She said a pre-construction review of the site with density sensors failed to detect the vaults, which are storage areas for items such as valves for gas lines and switches for electric and telecommunications systems.
Because of the project’s tight schedule to finish before a Pennsylvania Department of Transportation project starting later this summer, the city allowed the contractor to open trenches in more blocks rather than having the project sit idle during the vault work, Ms. Gaspich said.
As a result, many buildings on the north side of the street have fencing splitting the sidewalk where crews are actively working while others have trenches where the sidewalk has been jackhammered open. Still others have plywood panels covering the trenches. A few, especially in the 1000 and 1100 blocks, already have new utilities installed underground as well as the exposed aggregate sidewalk strip and bases for the new street lamps in place.
Read More
“Tuesday and Wednesday, we spent a lot of time taking down fences and restoring what we could for access,” Ms. Gaspich said. “The amount [of limited access to businesses] has been reduced as we’ve caught up.”
The city has done similar projects under its capital budget in Lawrenceville and Brookline in recent years, Ms. Gaspich said, but they covered smaller areas and required the street to be closed. This project covers 15 blocks and the goal was to keep the streets open for traffic and minimize disruption for businesses.
That can’t happen soon enough for some businesses.
“I hate it because it’s screwing up my business,” said David Johns, manager of the year-old Ethik LLC streetwear store in the 1400 block. “I work off of foot traffic. But overall, I think it’s a good thing. It’s not bad at all.”
Brandon McConnell, co-owner of One UP skate shop in the 1900 block for the past three years, said he’s disappointed at the timing of the project.
“I wish they could have done more while the weather was bad,” he said. “I’m just starting to get foot traffic after a bad winter. I like the idea of the greenery. It will all balance out.”
Ernie Sota, a contractor and board member of the South Side Chamber of Commerce, said members have had a mixed reaction to the early work.
One concern is how the new strips will look next to the remaining sidewalks, some of which are worn, or a variety of different material such as brick or concrete. The city didn’t have the money to do the entire sidewalk or a mechanism to have property owners contribute to help pay for the work.
“It’s going to be challenging as far as the long-term look is concerned,” he said. “We hope money can be found to do the rest of the sidewalk.”
For this project, almost all of the work is being done from 7 a.m. to 5 p.m.
But when the sidewalk work is done, PennDOT will begin a two-year project to repave the street, install new traffic signals and create bumpouts and more distinctive crosswalks at several intersections to improve safety. Much of that work will be done overnight.
“In the long run, the street is going to look nice when it’s done,” Mr. Sandi said. “But we’re retailers. We work day to day. Right now, it’s horrible.”