Excuse Pennsylvania Department of Transportation officials if you see them praying to the weather gods this week.
They need the weather to stay consistently above 25 degrees — with no major precipitation — so they can move ahead with a four-day inbound closure of the Parkway East between the Boulevard of the Allies/Liberty Bridge exit and the Grant Street on-ramp beginning at 6 a.m. Wednesday. It is scheduled to remain closed through 10 a.m. Sunday while work continues on Swank Construction Co.’s $26.2 million project to repave the highway from the Fort Pitt Bridge to the Edgewood-Swissvale exit.
If the weather cooperates, PennDOT is hoping that one, four-day closure of the inbound highway during Christmas week will inconvenience fewer motorists than five full weekend closures later in the year. Officials say about 40 percent fewer motorists use the highway during the holiday week.
Weather is crucial during the closure because crews want to replace concrete between the Allegheny County Jail and Grant Street. They want the temperature above 25 degrees so the concrete can cure before traffic is restored on the highway.
PennDOT and Swank scheduled the closure after struggling to get full weekends to do the work during the summer and fall because of various sports and large concerts that make it too inconvenient to close the roadway. As a result, with the time required to set up and take down barriers and stage equipment, crews haven’t been able to do a long stretch of work.
If crews can proceed this week, Swank will have four full days of work with only one setup and take down. That should allow crews to do enough work to eliminate five weekend closures during the normal construction season.
“We think long and hard about something like this before we do it,” Cheryl Moon-Sirianni, PennDOT district executive for the Pittsburgh area, said when the work was announced earlier this month. “We do think this is the way to have the minimum impact on the public.”
The work also is expected to include replacing dams on several bridges in the closure area and repairing concrete in the “bathtub” area beside the Monongahela Wharf, Downtown.
In addition to eliminating weekend work next year, the holiday week work also would clear the way for PennDOT to do summer work on feeder roads and roads used as detours for the Parkway East work.
This week’s work will force all inbound traffic to exit the Parkway East at the Boulevard of the Allies/Liberty Bridge exit beginning at 6 a.m. Wednesday. There will be different detours for cars and trucks. Police officers will be deployed along the detour routes to keep traffic moving.
For cars, the route involves following Interstate 579/Crosstown Boulevard to the Seventh Street exit and turning left on Grant Street to get to the parkway entrance.
Trucks have a different detour because they would have a difficult time making sharp turns on Downtown streets.
They will be rerouted across the Liberty Bridge, through the Liberty Tunnel, onto northbound Route 51/19 and follow the left-lane exit to Carnegie/Airport. Westbound trucks should stay right for the Parkway West but trucks headed Downtown should stay left and loop around to go through the Fort Pitt Tunnel.
The work will be done by 11 a.m. Sunday to allow motorists to use the highway to get to the Pittsburgh Steelers’ final home game against the Cincinnati Bengals.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.