The Pennsylvania Turnpike may have some extra money to pass along to other new construction after bids this week for the last section of the Southern Beltway came in about $25 million lower than the maximum estimate.
The turnpike received four bids for the complicated construction of the new toll road’s interchange with Interstate 79 in Cecil, including the apparent low bid from Walsh Construction Co. II at $174.3 million. Turnpike engineers had estimated the cost of the project — which involves digging pathways under the interstate for the new highway and installing bridges over the new valley — at between $150 million and $200 million.
“Any time you come in under is good news,” Steve Hrvoich, the turnpike’s construction engineering manager, said Thursday. “Any money left over from the Southern Beltway could be passed on to other projects like the Mon-Fayette [Expressway].”
The expressway, still under design, is a toll road that will link Route 51 in Jefferson Hills with the Parkway East in Monroeville.

Walsh Construction is part of the team that is building 558 small bridges under a $942 million public-private partnership with the Pennsylvania Department of Transportation. The other bidders were Trumbull Corp, $183 million; Beaver Excavating Co., $183.2 million; and Swank Construction Co., $188.4 million.
The interchange is the last major contract for the $800 million highway that will link I-79 and Route 22 along the Allegheny-Washington County border and provide an alternate route to Pittsburgh International Airport.
Read More
Since new construction such as the beltway comes from a separate fund, the independent project fund, any savings from lower-than-expected work can be passed on to similar projects.
Mr. Hrvoich pointed out that large projects such as the beltway include a contingency in the contract to cover routine overruns that occur due to unexpected items discovered during construction. Turnpike officials expect to review the bids for four to six weeks to make sure the contractor meets specifications before awarding the contract, so work likely won’t begin before spring.
“We don’t expect the final cost to be exactly what the bid was because there are always small changes along the way,” he said. “That’s why we have the contingency.”
Small changes can be paid for from the contingency fund with administrative approval from the turnpike but major cost increases must be approved by the turnpike commission.
The interchange project will involve moving all interstate traffic onto the northbound lanes of the highway while crews dig underneath the southbound lanes and install the southbound bridge. Then the process will repeat for the northbound lanes with all traffic shifted to the southbound side.
Overall, crews will move nearly 6.6 million cubic yards of dirt, each about the size of a refrigerator. In addition to the valleys under I-79, excavation will include digging under Morgan Road to flatten it out and create paths under it for the interchange ramps.
Work also will include: 190,106 square yards of long-life concrete pavement; 46,668 linear feet of drainage pipe; 23.558 linear feet of guiderail; 7 million pounds of fabricated structural steel; and 2.9 million pounds of epoxy-coated reinforcement bars.
Work to complete the interchange is expected to take until the summer of 2022, but most of the 13-mile, $800 million project could open as much as a year earlier when major connections between the interstate and the toll road are finished.
“Those are the major [connections] so we want to get those open as early as possible,” Mr. Hrvoich said. “This is the last piece of the puzzle.”
Remaining work would include a cloverleaf on Morganza Road that will be finished after the main line opens.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.