For the second time in three years, highway officials will deliver motorists the holiday equivalent of a lump of coal when they close part of the Parkway East the day after Christmas for major road work.

The Pennsylvania Department of Transportation announced Wednesday the highway will be closed to inbound traffic between the Boulevard of the Allies/Liberty Bridge exit and the Grant Street on ramp. If the weather cooperates, the road will be closed from 6 a.m. Dec. 26 to 11 a.m. Dec. 30 so crews can replace concrete between the Allegheny County Jail and Grant Street, as well as replacing dams on several bridges in that area and perhaps repairing concrete in the “bathtub” area beside the Monongahela Wharf, Downtown.

In 2015, Pittsburgh public works crews closed the highway in both directions during the same week for the implosion of the Greenfield Bridge, which has since been replaced.

PennDOT District 11 Executive Cheryl Moon-Sirianni said she hopes motorists will understand that doing work during the holiday week, when traffic is lower, will result in Swank Construction Co. eliminating five weekend closures next spring and summer. Swank has a $26.3 million contract to repave the highway from the Fort Pitt Bridge to the Edgewood-Swissvale exit.

Advertise with us

The contractor suggested the holiday-week closure because it has had trouble getting full weekends to work due to the many sports events and concerts in the city, Ms. Moon-Sirianni said. In addition, crews can eliminate the set-up time for overnight and weekend work if they can work straight through for more than four days.

Even this extended time will be limited because work will stop at 11 a.m. Dec. 30 to accommodate traffic for that day’s Steelers game at 1 p.m.

In addition to the inbound highway, inbound off-ramps at Second Avenue and Grant Street will be closed, as well as the inbound on-ramp from the Boulevard of the Allies to the Parkway East.

“We have a lot of problems getting weekends when there aren’t major events going on,” Ms. Moon-Sirianni said. “It becomes very inefficient for [the contractor] if they have to keep setting up and taking down all the time. They can be very efficient if they can just work straight through.”

Jason Zang, the assistant district executive for construction, said the concrete surface in this area hasn’t been replaced in about 34 years. Most other parts of the surface for overall project uses an asphalt overlay that can be milled and repaved in small sections at a time.

Advertise with us

Mr. Zang said the work will depend on the temperature that week. Crews can pour concrete as long as it is about 25 degrees or warmer using heaters and blankets, but it is difficult if it gets much colder.

“This is definitely weather-dependent,” Mr. Zang said. “We will watch the weather very closely the days before this is scheduled. If it looks too chancy, we’ll cancel it.”

The holiday closure won't be the end of Parkway East work, but it would help a lot, said Ms. Moon-Sirianni, noting that it is important for the parkway project to be finished as early as possible next year because other roads around the highway are scheduled for work during the summer. Crews can’t work on feeder roads and alternate routes while work is continuing on the highway, she said.

Beginning the day after Christmas, all inbound traffic on the Parkway East will have to exit at the Boulevard of the Allies/Liberty Bridge exit. Cars will follow Interstate 579/Crosstown Boulevard, exit at Seventh Street and turn left onto Grant Street to get back on the highway.

Trucks, which would have a difficult time handling sharp turns on Downtown streets, will be rerouted across the Liberty Bridge, through the Liberty Tunnel, onto northbound Route 51/19 and follow the left-hand exit to Carnegie/Airport. Trucks headed westbound should stay right for the Parkway West and left if they want to loop around and head Downtown through the Fort Pitt Tunnel.