With the chance of rainy weather this weekend, contractors are changing the type of work they will do on the Parkway East but outbound traffic near Downtown Pittsburgh still will be reduced to one lane.
Instead of milling and paving, Swank Construction Co. will do bridge dam replacement work between the Fort Pitt and Birmingham bridges from 10 p.m. Friday to 6 a.m. Monday. Outbound Parkway East traffic will be reduced from three lanes to one lane and entrance ramps from Downtown will be closed, along with the exit ramp to Oakland. Steve Cowan, spokesman for the Pennsylvania Department of Transportation District 11, said the Oakland ramp could open earlier if work progresses.
Milling and paving will be rescheduled for another weekend.
In addition, overnight work has been added this weekend under another contract to repair the joints where lanes come together between Churchill and Monroeville. That work will be done from 9 p.m. Friday to to 10 a.m. Saturday and from 6 p.m. 6 p.m. to 10 a.m. Sunday with temporary restrictions in areas where crews are working.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.






Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.