The Pennsylvania Department of Transportation is pulling out all stops to install a retaining wall and rebuild the collapsed section of Route 30 in East Pittsburgh by the end of June.
The department expects to award a contract Friday and issue a notice to begin work early next week as part of a “very aggressive” schedule, PennDOT District Executive Cheryl Moon-Sirianni said at a news conference Tuesday. Crews should begin the month-long installation of the wall in mid-May, followed by rebuilding the road in the 250-foot collapse area and several hundred feet on each side.
Plans call for 400-foot wall of precast concrete panels 20 feet tall that will be installed about 150 feet below the road surface. A wall in about the same location gave way April 7, when the roadway dropped about 30 feet. The collapse sent rocks and dirt cascading down the hillside, severely damaging two apartment buildings and two houses below.
The hope is to have about 20 displaced residents of the Electric Avenue Apartments return to the three remaining buildings of the complex by mid-June. They have been staying either with relatives or in hotels since they were evacuated after the hillside collapsed.
The East Pittsburgh landslide is part of a series of road problems caused by record rainfall since Feb. 15. Allegheny County on Tuesday declared a disaster so it can seek federal assistance to help pay for more than $12 million in damages from more than 70 landslides.
In East Pittsburgh, the wall and road construction is expected to cost $5 million to $7 million, but PennDOT already has been in touch with the Federal Highway Administration for emergency funding to pay for all aspects of the collapse. The highway, which carries 25,000 to 30,000 vehicles daily, is a key artery to the Parkway East from North Versailles, East McKeesport and North Huntingdon.
Read More
Ms. Moon-Sirianni credited consultant Gannett Fleming Inc. with quickly developing a preliminary design for remedial work. When soil samples and core borings to determine the depth of rock were different than anticipated, she said, the consultant adjusted the plans and posted documents late Monday for contractors to review and submit bids.
In developing the plans, Ms. Moon-Sirianni said, designers looked for the best and quickest option, even checking with suppliers to make sure steel needed for the project was available. Declaration of an emergency by the state allowed officials to cut red tape in areas such as obtaining rights of way, relocating utilities and obtaining clearances to begin work.
Jason Zang, PennDOT’s acting assistant director of construction, said the contract doesn’t include any incentives for finishing the project early because it is on such a tight schedule. There are potential penalties for finishing after June 30, but that end date could be extended if the contractor runs into unexpected delays.
“We have the schedule so aggressive now, we don’t see any way they can do it faster,” he said.
It will be up to the contractor whether crews work 24 hours a day and on weekends, he said.
The area where the collapse occurred and where the wall will be built is an anomaly in that part of the highway, Mr. Zang said.
In most of the area around the slide, the rock shelf begins about 9 feet underground, but where the slide occurred rock is as much as 60 feet deep, he said. In addition, it appears when the highway was built in the early 1930s, the area of the slide was covered with a lower grade of fill.
PennDOT gives an official update regarding the landslide along Route 30
To support the new wall, Mr. Zang said, crews will create pylons by drilling holes and filling them with concrete. Then steel posts will be installed horizontally through the concrete panels and into rock on the hillside to create anchors for additional support.
The hillside will by graded to a more gentle slope and granulated fill will be added to allow better drainage. Then — in the easiest portion of the process — new material will be placed for the subsurface of the road and a new surface will be laid in about two weeks at the end of June.
Ms. Moon-Sirianni said federal officials were in the area last week to review the site as part of the process of obtaining federal funds. The repair costs don’t include work done in the last 10 days such as clearing the landslide area, a task that has involved 250 truckloads of material already being hauled away with another 500 truckloads to come.
In addition, there are costs for emergency and permanent housing for displaced residents; design work by Gannett Fleming; the value of the destroyed apartments and houses; and emergency repairs to a culvert on Electric Avenue used by construction vehicles to get to the site. Those items are expected to add several million dollars to the cost of the project.
PennDOT engineers had been monitoring the roadway for about a month because the pavement was buckling, causing a series of lane restrictions before it was closed to traffic April 6. Officials were surprised when it collapsed the next morning, dropping three lanes of the road surface about 30 feet down the hillside above Electric Avenue.
“Trying to figure out where these slides are [going to occur] is very difficult,” Ms. Moon-Sirianni said. “Some of these that popped up in the past couple of days are in areas where we never expected a slide to happen.”
In his disaster declaration, Allegheny County Executive Rich Fitzgerald cited National Weather Service figures that show that from Feb. 15 to April 4, Pittsburgh International Airport recorded 9.68 inches of rain and Allegheny County Airport 8.68 inches. That doesn’t include more than 1.5 inches that fell Sunday and Monday.
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.