On a normal road or bridge project, the Pennsylvania Department of Transportation has to work with a variety or organizations: the Department of Environmental Protection; the state Fish & Boat Commission if a body of water is involved; utilities for relocation; local businesses to make sure a project isn’t too disruptive; public safety officials to maintain access; school districts for their transportation needs; and a series of subcontractors that supply various services.

Multiply that by 558 and you get a picture of the challenges Plenary Walsh Keystone Partners has faced under a public-private partnership with PennDOT to replace that many small, mostly rural bridges within three years for $899 million. The Rapid Bridge Project, one of the largest public-private partnership projects in the country, was designed to reduce the state’s inventory of structurally deficient bridges.

Plenary Walsh has completed about 400 bridges so far, but about 155 of the more complicated structures remain for 2018. As a result, the state has extended the completion date by four months through the end of next year and added $43 million to the contract to cover aspects of the delays that PennDOT officials say either were the department’s fault or the result of unforeseen circumstances.

“It’s an innovative project and it’s complicated,” said Michael Bonini, head of PennDOT's public-private partnership office. “Each bridge has its own story. Some of the bridges were more complicated than we thought.

Advertise with us

“It’s not unusual for a project of this size to have some overruns.”

The goal of the partnership is for Plenary Walsh to design and replace small bridges across the state using similar designs and materials, such as precast concrete beams, to create an economy of scale and ease of construction. In addition to construction, Plenary Walsh will be responsible for 25 years worth of maintenance on the bridges, which should last for 100 years.

But trying to replace that many bridges in a short period of time can create issues, said Edward Dice, head of delivery for Plenary Walsh. Among those issues:

• The need for hundreds of precast concrete beams taxed the production industry and Plenary Walsh worked to get additional in-state suppliers qualified to do government work.

• Many of the bridges cross trout streams, which means crews can’t work on them between spring and mid August.

Advertise with us

• Weather in the tropics caused some of the delays when some utility company crews that were expected to do relocation work — which must be done before bridge demolition and construction can begin — were diverted for weeks to help with hurricane relief in southern states.

In Lawrence County last week, crews used a 550-ton crane to lift a pair of 63,000-pound precast concrete beams into place on a two-span bridge over Little Neshannock Creek in Wilmington Township. Work on the bridge — one of the longest in the project at 155 feet with a pier in the middle — will be completed in 110 days, but it couldn’t begin until Aug. 15 because the creek is a popular fishing site.

To accommodate construction, crews created a temporary access road to the site that required plastic pipes to carry the creek under the road. The new span will replace a structurally deficient steel beam bridge that was built in 1952 and carries 1,237 vehicles a day.

As he watched the crews work, Mr. Dice said in many instances Plenary Walsh is completing bridges that in the past took PennDOT five to 10 years to replace.

“We didn’t know this bridge was gong to be replaced three years ago and we’re a month away from being done,” he said.

Advertise with us

The bridge is among a half dozen Plenary Walsh has replaced in the Wilkmington Township area, which has been a great benefit to the community, said Dan Vogler, chairman of the Lawrence County commissioners.

“The word rapid is accurate,” Mr. Vogler said. “They have addressed a good number of bridges and we’ve been very satisfied. The end result has been good.”

In addition to replacing deficient bridges, Mr. Dice said, the project has provided a huge boost to the state economy and led to several construction innovations such as using a polymer sealant to extend the life of the bridge surface and development of an electronic document management system. He estimated Plenary Walsh has spent more than $600 million across the state.

Mr. Bonini said PennDOT has been satisfied with the project, but it’s too early to say whether the department will conduct similar massive partnerships in the future. This venture has helped to reduce the state’s list of structurally deficient bridges from 6,034 in 2010 to 3,280.

“We’re pleased with where we are at this point with this partnership,” he said. “We’re anxious to see after 25 years whether the bridges are in better shape than if we took care of them ourselves and we anticipate they will be because that’s the way the contract was designed.”

Advertise with us

Mr. Dice said Plenary Walsh is similarly satisfied with the project.

“It’s a monumental task,” Mr. Dice said. “We might be building 150 bridges next year, but it’s the most complicated projects that would have taken a lot longer in the past.”

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.