A spokesman for the Pennsylvania Turnpike said there was "literally no traffic" backed up at the Cranberry and Beaver Valley interchanges Saturday night, a pleasant surprise considering that the road between the interchanges is closed this weekend, creating an 80-mile detour.

The turnpike closed at 9 p.m. Friday and is expected to remain closed through 4 a.m. Monday so crews from Brayman Construction Corp. and its subcontractors can dismantle a 150-foot bridge across Brush Creek in New Sewickley Township.

Once that's out of the way, workers are using paraffin to slide the new bridge from an adjoining platform onto the abutments. They'll then pave the approaches before the highway reopens.

It is the first time turnpike officials have used the innovative approach to bridge replacement, which has been effective in other states.

Advertise with us

Turnpike spokesman Carl DeFebo said crews were sliding the bridge segments into place just after 7 p.m.

"They’re on schedule, maybe a touch behind, but they hope to make time up overnight," Mr. DeFebo said.

The detour uses Interstate 80, sending traffic from the Cranberry interchange north on Interstate 79 and the New Castle interchange on Interstate 376. The detour takes a minimum of 90 minutes.

The process known as Accelerated Bridge Construction also will be used the weekend of Sept. 29 to replace a bridge on the Northeast Extension in Lehigh County.