The Pennsylvania Turnpike has tried to be in touch with everyone it can think of to make sure they know the toll road will be closed this weekend between the Cranberry and Beaver Valley interchanges. Even wedding planners and funeral directors.

The massive outreach also included radio and newspaper ads, billboards, and notifications to trucking and transportation companies.

In addition, the agency worked with the Ohio Turnpike and Pennsylvania Department of Transportation so they can help to notify motorists of the turnpike closure. It also sent notices to all 11,000 people who have emailed the agency this year and to EZ-Pass customers who have used the two interchanges recently.

As a result, the agency hopes none of the 40,000 motorists who use the highway every day will be surprised when they face an 80-mile detour.

Advertise with us

The turnpike will be closed from 9 p.m. Friday through 4 a.m. Monday while crews from Brayman Construction Corp. and its subcontractors dismantle a 150-foot bridge across Brush Creek in New Sewickley Township. Once that’s out of the way, they will use paraffin to slide the new bridge from an adjoining platform onto the abutments and pave the approaches before the reopens.

The detour will use Interstate 80, sending traffic from the Cranberry interchange north of Interstate 79 and the Beaver Valley interchange on Interstate 376. The detour likely will take a minimum of 90 minutes.

“We’re tried to reach out every way we can think of,” Kelli Roberts, the turnpike’s manager of marketing and business development, said Tuesday.

This weekend is the first time the turnpike has used the process known as Accelerated Bridge Construction, which previously has been used in other states. It also will use the procedure the weekend of Sept. 29 to replace a bridge on the Northeast Extension in Lehigh County.

The turnpike decided to use the accelerated procedure because closing the road completely for one weekend would be less disruptive than traditional construction that would require year-long traffic restrictions, said Wally Wimer, the turnpike's engineering project manager. Brayman crews have been building the new bridge on the adjacent platform since February and has “some things being tidied up this week,” Mr. Wimer said.

Advertise with us

“I know I’m excited about it,” he said. “I was out in the field last week while they repositioned the bridges. [The workers] all seem pretty calm and ready.”

The construction plan calls for the existing bridge to be dismantled by noon Saturday. Then crews will begin the process of sliding the new bridge into place, which could take as long as 12 hours, followed by attaching the new bridge, paving approaches and back-filling the staging area.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.

Since February, the contractor has been building the new bridge on a platform beside the existing structure along the turnpike and this weekend will demolish that bridge and slide the new one into place. (Darrell Sapp / Pittsburgh Post-Gazette)