An accident inbound (northbound) along the Parkway West at the runaway truck ramp in the Banksville area is slowing rush-hour traffic Friday morning.

The crash was reported shortly before 6:30 a.m. and is backing up traffic through Green Tree Hill, according to PennDOT.

Also, PennDOT officials Friday morning announced that the Liberty Bridge and inbound Liberty Tunnel will remain open all weekend. Previously scheduled weekend work has been canceled due to bad weather that’s being forecast. The work will be scheduled at a later date, said spokesman Steve Cowan.

Other traffic restrictions:

Advertise with us

Route 65/Ohio River Boulevard — Motorists will see lane restrictions on southbound Route 65 through Friday while crews repair damaged conduit. The restriction will be from 9 a.m. to 3 p.m. between the West End Bridge and the Fort Duquesne Bridge through Friday. Crews from the Lane Construction Corp. are doing the work.

Fort Duquesne Bridge ramps — Ramps from Allegheny and Ridge avenues to southbound Fort Duquesne Bridge (I-279) closed this weekend (July 21-23) beginning at 8 p.m. Friday night through 6 a.m. Monday. Also, the ramp carrying traffic from Reedsdale Street to the Fort Duquesne Bridge will close. The Reedsdale Street ramps to northbound Route 65 and Ridge Avenue will remain open. Detours will be posted.

McKnight Road/I-279 — Traffic shifted onto shoulder of the McKnight Road on-ramp to southbound I-279/Parkway North through late August. Crews from the Trumbull Corp. are replacing the bridge dam. Motorists should consider alternate routes including McKnight Road to Evergreen Road.

Stroschein Road, Monroeville — Closed through mid-November for replacement of the Dirty Camp Run Bridge No. 9 off Pitcairn Road. Traffic will be detoured using Northern Pike Road and Pitcairn.

Middle Road, Shaler/Hampton — Road reconstruction work from Saxonburg Boulevard (Shaler) to Harts Run Road (Hampton); works consists of base repairs, patching and road reconstruction and drainage.

Advertise with us

Library Road/Route 88, South Park — Single-lane alternating traffic for gas line replacement work, between Churchill Road and Royal Drive weekdays from 8 a.m. to 4 p.m., through July 21.

Warrendale Bayne Road/I-79, Marshall — Southbound I-79 on-ramp from Warrendale Bayne Road to close from 5 a.m. Saturday, July 22 through 6 a.m. Monday for resurfacing work. Detours will be posted.

Parkway North/I-279 — Traffic shifted into a single, 13-foot wide lane on the southbound I-279 ramp to northbound Route 65 (Ohio River Boulevard) through Aug. 21 for repair work. Trumbull Corp. is doing the work as part of the $87.94 million parkway improvement project.

Also, ongoing traffic re-configuration along the Parkway North south of the McKnight Road interchange:

▪ Two southbound lanes will continue to shift from the HOV lanes back into mainline I-279 near the Venture Street interchange.

Advertise with us

▪ A single-lane of the closed portion of the High Occupancy Vehicle (HOV) lanes will reopen to traffic:

▪ Motorists in the left-hand lane approaching the shift to mainline I-279 at Venture Street may choose to stay in the newly reopened HOV lane.

▪ Motorists using the HOV lane will only be able to use the slip ramp to southbound I-279 south of the I-579/Veterans Bridge exit. No access to Anderson Street or Stadium Drive will be permitted.

The 8.5-mile work zone from Camp Horne Road to the McKnight Road interchange will remain unchanged.

Western Avenue, North Side — Single-lane restrictions between Fulton Street and the West End Bridge weekdays from 7 p.m. to 2 p.m. the next day, through late July.

Advertise with us

Roberto Clemente Bridge (Sixth Street Bridge) — The bridge will be closed on some Fridays to accommodate Pirates games:

▪ On game days, the bridge will be closed to vehicular traffic starting at 2 p.m., and it will reopen to vehicular traffic one hour after the end of each game.

• Saturdays, Sundays and Holidays – On game days, the bridge will be closed to vehicular traffic at various times requested by the Pirates, and it will reopen to vehicular traffic one hour after the end of each game.

• Sidewalks on the Roberto Clemente and Rachel Carson bridges will be open for all games.

Liberty Bridge/Tunnels — Weekday lane restrictions on the bridge as crews continue to work on bridge reconstruction and steel repairs:

Advertise with us

▪ Two inbound lanes and one outbound open from 5 a.m. to 2 p.m.; one inbound and two outbound lanes from 2 to 7 p.m.; and one lane in each direction from 7 p.m. to 5 a.m.

Detours are posted.

Pearce Mill Road, McCandless -— Closed for waterline replacement project.

Interstate 376 — Long-term lane restrictions on westbound Interstate 376 in Findlay between Business Loop 376 West/Moon (Exit 57) and the Airport/East PA Turnpike 576 (Exit 53) interchanges, reduced to two 11 foot-wide lanes. The new configuration will be maintained through mid-November as crews reconstruct the concrete roadway, and conduct bridge and ramp repairs.

▪ Also, westbound I-376 off-ramp to Business Loop 376 West/Moon (Exit 57) will be reduced to a single-lane lane through mid-November. The ramp will remain open as crews conduct roadway reconstruction work.

Advertise with us

Other restrictions in that area include:

▪ Intermittent single-lane restrictions eastbound (inbound) between Beaver County line and the McClaren Road (Exit 56) interchange, weekdays from 7 a.m. to 3 p.m. westbound and 9 a.m. to 5 p.m. eastbound as crews from Swank Construction begin median crossover work as part of the $66.3 million reconstruction project.

Route 22, Monroeville — Single lane restrictions on Route 22 over Thompson Run Road in each direction from 7 a.m. to 3 p.m. weekdays through Friday, Aug. 4.

Route 65/Ohio River Boulevard -— PennDOT has announced long-term lane restrictions on northbound Route 65/Ohio River Boulevard as part of a $25.3 million improvement project:

▪ A lane will be closed from Fort Duquesne Bridge to the West End Bridge and from West End Bridge to the McKees Rocks Bridge. Around-the-clock closure lasts through Sept. 7. Two 11-foot lanes will be maintained. Work will include concrete patching, an asphalt overlay, bridge reconstruction, base repairs, drainage and guide rail updates, new signs, retaining wall repairs and pavement-marking installation.

Advertise with us

▪ Single lane overnight in both directions between 7 p.m. and 6 a.m. Tuesday through Thursday nights for milling and resurfacing activities.

Wabash Tunnel — Inbound tunnel will be open at 5 a.m. weekdays and just after 2:30 p.m. for outbound motorists to help ease congestion caused by the Liberty Bridge construction projects. HOV vehicle occupancy restrictions will be lifted during the extended hours of operation.

McClaren Road, Findlay — McClaren Road closed between Garden Lane and Mustang Drive through mid-November so crews from Golden Triangle Construction to conduct road reconstruction and bridge repairs.

Interstate 79, Butler County — Lane closures in each direction during off-peak hours, between 6 p.m. and 6 a.m. daily with two exceptions. On Fridays, work in the northbound lanes will start at 9 p.m. and on Sundays work in the southbound lanes will be start at 9 p.m., through October.

Ligonier — A lane restriction on Route 711 between Slater Road and Peters Road in Ligonier Township, Westmoreland County for bridge repairs. Project scheduled to last through Aug. 17. Wilpen Road (Route 1017) and Marietta Road (Route 1019) will be closed. Detours will be posted.

Advertise with us

Russellton-Dorseyville Bridge, West Deer — Bridge replacement work has closed Russellton-Dorseyville Road between Saxonburg Boulevard and East Union Road around-the-clock through late August. Detours are posted.

Warrendale Bayne Road, Marshall — Lane closures as part of a $1.28 million road improvement project will last through October:

• Intermittent single-lane alternating traffic will occur as needed on weekdays from 9 a.m. to 3 p.m. and weeknights from 7 p.m. to 6 a.m. as crews conduct the work at intersection with Brush Creek Road/southbound I-79 on-ramp, and at intersection with Innovation Drive. A single lane in each direction will be maintained during peak travel times. The southbound I-79 ramp will remain open during construction. Crews from Frank J. Zottola Construction, Inc. will conduct roadway widening, milling and paving, drainage improvements, sidewalk improvements, signal upgrades and pavement marking installation.

Glenwood Bridge — The next phase of the $17 million Glenwood Bridge interchange rehabilitation project involves the following restrictions:

▪ Around-the-clock single-lane restriction through November in each direction of Route 885 for bridge work over the northbound Route 837 ramp to southbound Route 885. One lane of Route 885 will remain open in each direction.

Advertise with us

▪ Southbound Route 837 ramp to northbound Route 885 will be closed to traffic around-the-clock through late July. Traffic will be detoured.

▪ Around-the-clock single-lane closure on northbound Route 885 in the area of the closed southbound Route 837 ramp to northbound Route 885, through November. One lane will remain open on northbound Route 885.

▪ Route 837 traffic to southbound Route 885 will detoured at the Hot Metal Bridge, but southbound Route 837 traffic may continue to Becks Run Road.

▪ Also, four weekend closures will occur. PennDOT says more information will be provided once the closures are scheduled.

Andy Warhol Bridge — Closed to vehicular and pedestrian traffic through November as part of $25.4 million rehabilitation project. The Rachel Carson Bridge (9th Street) will be used as a detour. The detour also will reroute about 350 Port Authority buses a day to Carson, according to the Port Authority. The detoured routes will be routes 1, 2, 4, 6, 7, 8, 11, 12, 13, 15, 16, 17 and the O5. The Carson Bridge is expected to be rehabbed in 2018 and the Clemente Bridge in 2020.

Advertise with us

Clifton Road, Bethel Park — Gas line work will restrict the road to single-lane, alternating traffic between Kings School Road and Brush Run Road from 9 a.m. to 3 p.m. weekdays through Aug. 15. Also single-lane alternating traffic on Irishtown Road/Braun Road during the same period.

Liberty Interchange (Routes 51 and 19) — Overnight closures as part of a $4.3 million improvement project of the south portal of the Liberty Tunnel at Route 51 (Saw Mill Run Boulevard) and Route 19 (West Liberty Avenue) interchange. Work will occur weeknights from 8 p.m. to 5 a.m. and on weekends from 8 p.m. Friday night continuously through 5 a.m. Monday morning, through July, in the following locations:

▪ Route 51 between Bausman Street and Crane Avenue

▪ Route 19 between Pioneer Avenue and the Liberty Tunnel

I-376 cashless tolling — The Pennsylvania Turnpike Commission has begun using cashless tolling on a stretch of Interstate 376 known as the Beaver Valley Expressway.

Advertise with us

The 16.5-mile tolled portion of Interstate 376 between Chippewa and New Castle will have no toll collectors. Motorists who don’t have an E-ZPass transponder will have a photograph taken of their license plate and receive a bill once a month similar to a credit card payment with 20 days to pay.

The billing cycle will start the first time a driver goes through the toll booth without a transponder and a bill will be issued 30 days later. Users of E-ZPass will have fares deducted from their account as usual.

Cavasina Drive, Canonsburg — Northbound lane closure at the intersection with Route 1009/Morganza Road and Route 1025/Weavertown Road in Canonsburg/North Strabane through Sept. 14 to allow crews to perform intersection widening and traffic signal upgrades.