PennDOT said that it should be ready to announce a timeline for repairs needed for the Liberty Bridge today after a fire damaged a stretch of the bridge and put its stability in jeopardy on Friday afternoon.
A 30-foot beam underneath the structure buckled in the intense heat of the blaze, forcing PennDOT to shut down the bridge to traffic at least through the weekend and place it under around-the-clock monitoring out of concerns for public safety.
The fire broke out about 1 p.m. Friday when workers cutting steel and using blowtorches sent sparks flying, subsequently igniting a tarp draped to control a painting operation. It spread to plastic piping that burned so hot it melted a steel beam, or chord, underneath the bridge. Pittsburgh firefighters put out the blaze in about half an hour.
PennDOT said Saturday that preliminary designs for the bridge repair were developed overnight Friday, and the contractor was in the process of getting the necessary materials.
“PennDOT anticipates a final design and a timeline for repairs will be complete on Sunday,” PennDOT said in a statement. “Once the final design is determined, the department will hold a press conference to share the details of the repair and the anticipated schedule to complete the repair and reopen the bridge.”
The bridge, built in 1928, was already undergoing a two-year, $80 million renovation project that began in March, the first major work on it since 1986. The work includes deck replacement and ramp reconstruction, structural steel repairs, painting of the entire structure, concrete repairs, signage improvements and installation of a new alternating overhead lane-control system.
Read More
Authorities halted commercial river traffic from passing underneath the bridge for about 20 hours during and after the fire, PennDOT said, because even a small bump to the bridge could cause major problems given the critical damage to the beam. Commercial river traffic resumed Saturday after PennDOT collaborated with the Waterways Association of Pittsburgh and the U.S. Coast Guard, which has issued protocols for passing barges.
The Liberty Bridge is a major artery over the Monongahela River between Downtown and the South Hills. Traffic is being detoured through the Fort Pitt Bridge while the Liberty Bridge remains closed.
The Liberty Bridge and inbound Liberty Tunnel is expected to remain closed at least through Monday, but the outbound Liberty Tunnel has remained open to vehicles coming down P.J. McCardle Roadway and turning right toward the South Hills, PennDOT said.
Many major roadways in and around the city were gridlocked on Saturday as fans poured into the North Shore for the Pitt football game at Heinz Field during the afternoon and the Pirates game at PNC Park during the evening. The Heinz Field Rib Fest also continued on Saturday.
Traffic in the North Shore was further complicated as the Roberto Clemente Bridge was closed for the Pirates game and the Andy Warhol Bridge remains under construction.
Dan Cessna, executive director for the PennDOT district that covers Pittsburgh, said that work is being done vigorously to ensure the Liberty Bridge can reopen to traffic as soon as possible.
“Our PennDOT engineers and inspectors, in cooperation with staff from contractor Joseph B. Fay, consultant engineers and inspectors from SAI Consulting Engineers, Inc., HDR, Inc. and Michael Baker International, and faculty and research staff from Lehigh and Carnegie Mellon universities have been engaged in investigating, stabilizing, inspecting, designing and preparing for the repair of the Liberty Bridge,” Mr. Cessna said in a statement. “The team has been focused around-the-clock on developing the most effective temporary repair to expedite the reopening of the bridge.”