To Bev Collier, it means an easier trip to work. Nancy Jacobs can resume trips to the Strip District after a nearly three-year lull. For Wayne Masters, it might be the lifeline to help rejuvenate his childhood neighborhood.
That’s what the weekend’s quiet reopening of West Carson Street to two-way traffic between Pittsburgh’s South Side and the city’s West End and western suburbs means to those who use it regularly. The project to ease traffic at the West End Circle was expected to be a two-year effort when it began in 2013, but underground utility lines that were found in different places than shown on maps delayed the project for an extra year while the lines were moved.
“I was ecstatic to see it was open on Saturday,” said Ms. Collier of Sheraden, who works for the Green Building Alliance on the South Side. “[The construction] has been a major obstacle. I couldn’t be more thrilled.”
West Carson was limited to one lane inbound and carried no outbound traffic through the duration of the project. Ms. Jacobs, a senior citizen from McKees Rocks, said she avoided the area as much as possible.
“It did deter me from going to the Strip District or Downtown just for pleasure,” Ms. Jacobs said. “It was just inconvenient. I’m sure I will use it now to get to the Strip District again.”
Mr. Masters of Stowe sees the project, which takes traffic beneath the West End Circle to provide better flow and less congestion in the circle, as a boon to McKees Rocks and Stowe. Some neighborhoods in those municipalities have fallen on hard times since he grew up there, moved to California in the 1970s and returned to the area last year to maintain the family homestead in the Presston neighborhood.
“I just drove this morning from McKees Rocks to the South Side and back. It’s an awesome job,” said Mr. Masters, who sent a thank-you letter to contractor Lane Construction. “I’d like to see Stowe and McKees Rocks become family communities again, and this will help.”
PennDOT spokesperson Steve Cowan said Lane has punch-list items to complete and there could be temporary lane shifts and closures as the project is wrapped up. The location of utilities was not anyone’s fault because that work had been done “decades and decades ago,” he said.
The delays added to the cost of the $39 million project, but Mr. Cowan didn’t have the exact final cost Monday.
Mr. Cowan drove on West Carson shortly after it opened Saturday and found it nearly empty. “People just didn’t realize it was open.”
Ed Blazina: eblazina@post-gazette.com or 412-263-1470.