PennDOT is opening up two outbound lanes on the Liberty Bridge and Tunnel tonight to accommodate fans leaving the Coldplay concert at Consol Energy Center.

And instead, the inbound/northbound bridge and tunnel will be closed beginning at 8 tonight through 5 a.m. Friday so crews can continue work on the bridge rehab project.

Friday morning, the traffic configuration will then shift back to two inbound lanes and one outbound lane open.

Other traffic restrictions around the region:

Advertise with us

Route 28 ramp, East Ohio Street — The on-ramp that carries traffic from East Ohio Street to northbound Route 28 is closed around-the-clock through Nov. 9. The ramp will be reconstructed with a new deck and a wall will be repaired. Detours are posted: from East Ohio, turn onto Chestnut Street and cross the 16th Street Bridge, turn left onto Liberty Avenue, left onto 31st Street Bridge, right onto the ramp to northbound Route 28. The East Ohio Street ramp from southbound Route 28 reopened July 30.

Camp Horne Road, Emsworth — Will close for construction work beginning Aug. 15, about a quarter-mile north of the Camp Horne Road and Ohio River Boulevard/Route 65 intersection. Crews will rebuild a retaining wall. Traffic will be detoured using Mount Nebo Road, Interstate 79 and Ohio River Boulevard. The project is scheduled to be completed by mid-November.

Squirrel Hill Tunnel — Overnight single-lane closure inbound (westbound) in the Squirrel Hill Tunnel from 10 p.m. Friday night to noon on Saturday. Crews from Lighthouse Electric Co. will continue drilling and conduit installation work to restore cell phone service inside the tunnel. Single-lane restrictions may also occur outbound.

Bridge washing — Single-lane restrictions as needed weeknights from 8 p.m. to 6 a.m. through Friday (Aug. 12) on the ramp from the 10th Street Bypass to the Fort Duquesne Bridge; the ramp from Fort Duquesne Boulevard to the Fort Duquesne Bridge; and the ramp from the Fort Duquesne Bridge to Reedsdale Street.

Andy Warhol Bridge -- Closed to vehicular and pedestrian traffic beginning at 9 a.m. Aug. 15 through November 2017 as part of $25.4 million rehabilitation project. The Rachel Carson Bridge (9th Street) will be used as a detour. The Roberto Clemente (6th Street) Bridge will still be closed before and after Pittsburgh Pirates home game.

Advertise with us

West Carson Street — Closed from Stanhope Street to the West End Circle. PennDOT expects the road to reopen in late August/early September. Remaining work includes:

Grinding concrete for a smooth ride and texture, dawing and sealing all joints, installing highway lighting, completing railing, finishing wall repairs, and pavement markings including crosswalks.

Mon-Fayette Expressway meetings —  The Pennsylvania Turnpike Commission will hold four public meetings to discuss revised plans for the Mon-Fayette Expressway extension from Jefferson Hills to Monroeville. The hearings, which run from 6 to 8 p.m., will be held:

• Aug. 9, Skyview VFD, 660 Nobel Drive, West Mifflin;

• Aug. 10, St. Agnes Center, Carlow University, 3325 Fifth Ave. Oakland;

Advertise with us

• Aug. 16, Gateway Middle School gym, 4450 Old William Penn Highway, Monroeville;

• Aug. 17, Woodland Hills High School, 2550 Greensburg Pike, Churchill.

Neville Island/I-79 — Inspection work on on-ramp to I-79 south today through Friday (Aug. 5), weather permitting, from 9 a.m. to 3 p.m. each day. The ramp will remain open to traffic.

Route 65/Ohio River Boulevard — A long-term closure through September of southbound Route 65/Ohio River Boulevard between the Beaver Avenue Exit ramp and the West End Bridge. Construction crews will rebuild the highway between the McKees Rocks and Fort Duquesne bridges in the latest step in a two-year, $25.3 million project. Southbound Route 65 traffic will be detoured: Motorists can follow Beaver Avenue to the Interstate 279-376 ramp to Downtown Pittsburgh and back to Route 65 inbound or stay on Beaver Avenue to the North Side. A police officer will be stationed at a traffic light on Beaver Avenue to help keep traffic moving, PennDOT said.

Crews will switch to the outbound side of the highway next spring and expect to finish work by September 2017.

Advertise with us

The $25.2 million improvement project will include concrete patching, an asphalt overlay, bridge rehabilitation, drainage and guiderail updates, signage, retaining wall repairs and pavement marking installation.

Campbells Run Road, Carnegie — Closed for work on a landslide area at the intersection of Highland Avenue. Traffic will be detoured using the Parkway West, Rosslyn Road, and Baldwin Road. The project is scheduled to be completed by next spring.

Pine Creek Road, McCandless — Bridge that carries Pine Creek Road over Pine Creek in McCandless is closed through Sept. 13. Detours have been posted, taking traffic from Route 19 to West Ingomar Road, Highland Road and eventually back to Pine Creek Road. Crews from Carmen Paliotta Constructing and Frank J. Zottola Construction will perform the work at the intersection with Route 19/Perry Highway.

Route 978/Battle Ridge Road, South Fayette — Waterline replacement: single-lane alternating traffic from Fryes Lane to Dutch Hill Road weekdays from 9 a.m. to 4 p.m. through Oct. 16. Flaggers will control traffic.

East Pennview Street, Shaler — Closing for bridge replacement to begin Aug. 11. Pine Creek Bridge No. 11 is about a quarter of a mile west of the intersection of Pennview and Route 8. Closure in place until spring 2017.

Advertise with us

Piney Fork Road, Jefferson Hills/South Park — Closed through the end of August between Gil Hall Road and Snowden Road. Crews from Lone Pine Construction Inc. are building a railroad bridge for Wheeling & Lake Erie Railway over Piney Fork Road. Detours will be posted.

Bloomfield Bridge — Single-lane restrictions in each direction weekdays from 10 a.m. to 3 p.m.; and on Blessing Street through Aug. 5.

Liberty Bridge — The next phase of the Liberty Bridge rehabilitation project has begun and with new traffic patterns, including the opening of two outbound lanes that will be separated by a work lane. Under the construction plan, traffic patterns are changed three times a day:

▪ Two inbound (northbound) lanes and one outbound (southbound) lane will be open from 5 a.m. to 2 p.m. each weekday.

▪ Two outbound (southbound) lanes and one inbound (northbound) lane will be open from 2 p.m. to 8 p.m. each weekday.

Advertise with us

▪ One lane open in each direction from 8 p.m. to 5 a.m. each weeknight.

▪ Work may occur on Saturdays and Sundays. Additional information will be provided if work occurs.

In addition, McArdle Road from Arlington Avenue will be open to two lanes of traffic during this phase of the project. It had been reduced to one lane.

In addition, PennDOT reminds motorists that the ramp from the Boulevard of the Allies to the Liberty Bridge has been reduced to one lane and has a stop sign instead of a merge. Also, southbound traffic on Interstate 579 is reduced to one lane approaching the Boulevard of the Allies and the bridge and also has a stop sign.

East Ohio Street, North Side — Long-term single-lane restrictions in each direction on East Ohio Street between Nash Street and Chestnut Street for roadway reconstruction and expansion dam work, through late September.

Advertise with us

Route 885/Clairton Road, West Mifflin — Single-lane alternating traffic between College Drive and Ravensburg Boulevard from 8 a.m. to 6 p.m. weekdays. Weekend work from 8 a.m. to 8 p.m. may occur. Flaggers will assist motorists through the work zone.

Fox Chapel Road — Closed between Guys Run Road and Delafield Road from 7 a.m. to 7 p.m. daily for drainage repairs, milling, paving and guiderail improvements through October.

McKnight Road, McCandless — Single-lane closures will occur as needed on northbound McKnight Road weekdays from 9 a.m. to 3 p.m. through July 27. Crews from the Brayman Construction Corp. will conduct roadway pavement marking installation and bridge and pipe work between West Arcadia Road and Pine Creek Road. The work is part of the $7.3 million project to improve three existing bridges carrying McKnight over Ingomar Road, Pine Creek, and Route 19.

Venetia Bridge, Peters — The bridge is closed through mid-September so that it can be replaced. A detour is posted.

Rankin, Swissvale — Single-lane alternating traffic between Fifth Avenue in Rankin Borough and Woodstock Avenue in Swissvale for drilling work, weekdays from 9 a.m. to 3 p.m. and from 7 a.m. to 7 p.m. on weekends, through Sept. 4.

Advertise with us

O’Neil Boulevard, McKeesport — Closed as part of a slope stabilization project near Porter Street. Detour uses Eden Park Boulevard, Walnut Street, 30th Street and Patterson Street.

McLaughlin Run Road, Bridgeville and Upper St. Clair — There will be alternating single-lane traffic weekdays from 9 a.m. to 3 p.m. and from 7 p.m. to 6 a.m. while crews conduct road improvements on McLaughlin Run Road between Bower Hill Road and Washington Road (Route 19).

Wildwood Road, Hampton — Closed between Roland Road/Trillium Trail and Grouse Run Road as crews conduct the first phase of slide remediation work. The second phase of work will close Wildwood Road between Roland Road/Trillium Trail and Sylvan Drive through November. Detours are posted. Crews are working around-the-clock on a $2.6 million project to secure two landslide areas.

Cranberry — Overnight work on Freedom Road/ Valley Forge Road and Parkwood Road intersection begins Aug. 15, from 8 p.m. to 6 a.m.

Route 51/Route 201, Rostraver — Lane closures from around Vernon Drive in Rostraver to the Allegheny County line. The contractor, Golden Eagle Construction, is working on milling and base repairs.

Advertise with us

Baum Boulevard bridge — The traffic pattern for the Baum Boulevard Bridge deck replacement has changed and the road closed from Melwood Avenue and Enfield Street in Bloomfield to Melwood and Gold Way. After bridge repairs are made, the boulevard from the bridge to Morewood Avenue will be closed for resurfacing. The entire project is expected to cost $12.3 million and should wrap up sometime in August.

Steubenville Pike (Route 60), Robinson and Crafton — There will be single-lane traffic restrictions on Route 60 between the intersection of Noble Avenue/East Steuben Street and Lorish Road weekdays from 9 a.m. to 3 p.m. and from 7 p.m. to 6 a.m.

Greensburg Pike, North Versailles — Greensburg Pike will be closed until mid-August for road and ground stabilization work near the Save-A-Lot grocery store in the Great Valley Shopping Center. A. Merante Contracting Inc. will construct a jumbo block reinforced geo-grid wall as part of the $590,000 project. Traffic approaching the site from Turtle Creek will be detoured through the shopping center to Route 30. Access to Greensburg Pike from Route 30 will be limited to local traffic.

Mt. Lebanon Boulevard -- Closed between Washington Road (Route 19) and Rocklynn Place weekend of Aug. 5-7.

Noblestown Road/Route 50 — Single-lane alternating traffic will occur from 9 a.m. to 3 p.m. and 7 p.m. to 6 a.m. Monday through Friday, and possibly during weekends along Noblestown/East Main Street in Scott, Green Tree, Carnegie and Pittsburgh for road resurfacing. Crews from Lane Construction have begun work between the intersection of East Main Street and Washington Avenue in Carnegie and the intersection of Noblestown and Poplar Street in Green Tree. The project is scheduled to be completed in early August.

Advertise with us

Red Line, Beechview — Section of the Red Line of Port Authority light-rail system that runs through Beechview is closed as part of a T reconstruction project. The Port Authority is replacing rails embedded in Broadway Avenue between Potomac and Fallowfield avenues, which will affect about 12,000 commuters who use the Red Line to get to Downtown and other locations.

The Red Line will operate as normal from Fallowfield to Downtown and the North Shore. To accommodate passengers from other parts of Beechview and the South Hills, Port Authority has offered several options.

▪ In the construction zone, a free shuttle bus will run every 12 minutes during rush hours (6-9 a.m. and 4-6:30 p.m.) and every 30 minutes during other service hours.

▪ A free rail shuttle will run from Potomac to the Blue Line at Overbrook every 12 minutes in rush hours, every 20 minutes during the day and every 30 minutes in the evening.

▪ A temporary bus route, 42 Dormont, will run between the Mt. Lebanon station and Downtown via West Liberty Avenue during weekday rush hours.

Advertise with us

The contractor hired for the project will work Monday through Saturday, from 6 a.m. to 11 p.m.

Interstate 70 — PennDOT has seven projects under way on the 32-mile stretch of Interstate 70 between Eighty Four in Washington County and New Stanton in Westmoreland County. The I-70 work is part of a multi-year series of projects to upgrade the highway. Traffic near the 1-70/​Route 19 interchange moved to the eastbound lane with two lanes in each direction.

Smithfield Street, Downtown — Northbound travel lane and parking lane closed from Fourth to Fifth avenues for the reconstruction of the Forbes Avenue and Smithfield Street intersection. The closure is expected to last through the summer.