The next phase of the Liberty Bridge $80 million rehabilitation project begins this morning.

The traffic pattern will change with the inside northbound/inbound lanes on bridge closed to traffic for about 30 days as crews replace the deck. The work will take place one lane at a time through four separate work phases, according to PennDOT. During each phase, the traffic configuration will changed three times each weekday. Three lanes of traffic will be open during peak travel times and two lanes will be maintained overnight.

The traffic patterns and schedule:

▪ Two inbound (northbound) lanes and one outbound (southbound) lane will be maintained from 5 a.m. to 2 p.m. each weekday.

Advertise with us

▪ Two outbound (southbound) lanes and one inbound (northbound) lane will be maintained from 2 p.m. to 8 p.m. each weekday.

▪ A single-lane of traffic will be maintained in each direction from 8 p.m. to 5 a.m. each weeknight.

▪ Work may occur on Saturdays and Sundays. Additional information will be provided if work occurs.

The inbound (northbound) Liberty Bridge ramp to the Boulevard of the Allies reconstruction work will continue during this new phase. The ramp will remain closed and traffic will continue to be detoured. The ramp is anticipated to reopen by July 8.

More project details are available via PennDOT’s website here.

Advertise with us

Other traffic restrictions around the region:

Route 65 — Long-term closure of southbound Route 65 will begin at 9 a.m. on Wednesday between the Beaver Avenue Exit ramp and the West End Bridge. Crews will conduct mainline bridge rehabilitation through mid-September. Southbound Route 65 traffic will be detoured.

Squirrel Hill Tunnel — Single-lane restriction inbound (westbound) Squirrel Hill Tunnel weeknights from 10 p.m. to 5 a.m. through July 8. Crews from Lighthouse Electric Company will begin drilling and conduit installation work to restore cell phone service inside the tunnel.

Fort Pitt Tunnel/Parkway West -— Full inbound (eastbound) I-376/Parkway West closure from I-79 to Parkway Center Drive and a lane closed outbound (westbound) between the Greentree/Crafton (Exit 67) and I-79 (Exit 64A) interchanges, weeknights from 9 p.m. to 6 a.m. through Friday night.

Also, tonight outbound Fort Pitt Tunnel closes and Wednesday night the inbound tunnel will close overnight from 9 p.m. to 6 a.m.

Advertise with us

West Carson Street, South Side — A section of West Carson Street on the South Side will remain closed through at least Wednesday from the Fort Pitt Bridge to Station Square/Commerce Street after a rockslide earlier this week made a hillside unstable, PennDOT officials said. Traffic is allowed from the West End Circle to the Fort Pitt Bridge on-ramp.

PennDOT officials said geotechnical engineers continue to evaluate the hillside. Several boulders fell onto the street early Tuesday morning, one of which struck a vehicle. The driver was unhurt but the front end of car sustained damage, authorities said.

Detours are as follows: From West Carson heading east, motorists will take the Fort Pitt Bridge ramp, follow Parkway East/I-376 eastbound to the Forbes Avenue/Oakland (Exit 72A) off-ramp; turn left onto Craft Avenue, turn left onto Fifth Avenue, turn left onto the Birmingham Bridge, follow back to East Carson Street.

From East Carson Street, turn right onto South 10th Street and cross the bridge, turn right onto Second Avenue, turn left onto Bates Street, turn left onto the Boulevard of the Allies, take Fort Pitt Bridge ramp, from bridge take ramp to north Route 837/Route 51 West End.

East Ohio Street, North Side — Long-term single-lane restrictions in each direction on East Ohio Street between Nash Street and Chestnut Street for roadway reconstruction and expansion dam work, through late September.

Advertise with us

Route 885/Clairton Road, West Mifflin — Single-lane alternating traffic between College Drive and Ravensburg Boulevard from 8 a.m. to 6 p.m. weekdays. Weekend work from 8 a.m. to 8 p.m. may occur. Flaggers will assist motorists through the work zone.

Fox Chapel Road — Closed between Guys Run Road and Delafield Road from 7 a.m. to 7 p.m. daily for drainage repairs, milling, paving and guiderail improvements through October.

Pine Creek Road, McCandless — Bridge that carries Pine Creek Road over Pine Creek in McCandless is closed through Sept. 13. Detours have been posted, taking traffic from Route 19 to West Ingomar Road, Highland Road and eventually back to Pine Creek Road. Crews from Carmen Paliotta Constructing and Frank J. Zottola Construction will perform the work at the intersection with Route 19/Perry Highway.

McKnight Road, McCandless — Single-lane closures will occur as needed on northbound McKnight Road weekdays from 9 a.m. to 3 p.m. through July 27. Crews from the Brayman Construction Corp. will conduct roadway pavement marking installation and bridge and pipe work between West Arcadia Road and Pine Creek Road. The work is part of the $7.3 million project to improve three existing bridges carrying McKnight over Ingomar Road, Pine Creek, and Route 19.

Venetia Bridge, Peters — The bridge will be closed beginning July 7 through mid-September so that it can be replaced. A detour will be posted.

Advertise with us

Liberty Bridge — Inside northbound/inbound lane on the Liberty Bridge will close to traffic for about 30 days as crews do deck replacement work. The deck will be replaced one lane at a time through four separate work phases. During each phase of construction, the traffic configuration will be changed three times each weekday. Three lanes of traffic will be maintained during peak travel times and two lanes will be maintained overnight. The traffic patterns will occur according to the following schedule:

▪ Two inbound (northbound) lanes and one outbound (southbound) lane will be maintained from 5 a.m. to 2 p.m. each weekday.

▪ Two outbound (southbound) lanes and one inbound (northbound) lane will be maintained from 2 p.m. to 8 p.m. each weekday.

▪ A single-lane of traffic will be maintained in each direction from 8 p.m. to 5 a.m. each weeknight.

▪ Work may occur on Saturdays and Sundays. Additional information will be provided if work occurs.

Advertise with us

The inbound (northbound) Liberty Bridge ramp to the Boulevard of the Allies reconstruction work will continue during this new phase. The ramp will remain closed and traffic will continue to be detoured. The ramp is anticipated to reopen by July 8.

O’Neil Boulevard, McKeesport — Closed as part of a slope stabilization project near Porter Street. Detour uses Eden Park Boulevard, Walnut Street, 30th Street and Patterson Street.

McLaughlin Run Road, Bridgeville and Upper St. Clair — There will be alternating single-lane traffic weekdays from 9 a.m. to 3 p.m. and from 7 p.m. to 6 a.m. while crews conduct road improvements on McLaughlin Run Road between Bower Hill Road and Washington Road (Route 19).

Wildwood Road, Hampton — Closed between Roland Road/Trillium Trail and Grouse Run Road as crews conduct the first phase of slide remediation work. The second phase of work will close Wildwood Road between Roland Road/Trillium Trail and Sylvan Drive through November. Detours are posted. Crews are working around-the-clock on a $2.6 million project to secure two landslide areas.

Franklin Park -- Warrendale-Bayne Road between Mingo Road and Big Sewickley Creek Road for repaving work through mid-July.

Advertise with us

Sewickley Heights -- Blackburn Road between Fern Hollow Road and Hill Street, wall repairs and paving that will include a road closure and detour will start in mid-July.

Baum Boulevard bridge — The traffic pattern for the Baum Boulevard Bridge deck replacement has changed and the road closed from Melwood Avenue and Enfield Street in Bloomfield to Melwood and Gold Way. After bridge repairs are made, the boulevard from the bridge to Morewood Avenue will be closed for resurfacing. The entire project is expected to cost $12.3 million and should wrap up sometime in August.

Steubenville Pike (Route 60), Robinson and Crafton — There will be single-lane traffic restrictions on Route 60 between the intersection of Noble Avenue/East Steuben Street and Lorish Road weekdays from 9 a.m. to 3 p.m. and from 7 p.m. to 6 a.m.

Greensburg Pike, North Versailles — Greensburg Pike will be closed until mid-August for road and ground stabilization work near the Save-A-Lot grocery store in the Great Valley Shopping Center. A. Merante Contracting Inc. will construct a jumbo block reinforced geo-grid wall as part of the $590,000 project. Traffic approaching the site from Turtle Creek will be detoured through the shopping center to Route 30. Access to Greensburg Pike from Route 30 will be limited to local traffic.

Noblestown Road/Route 50 — Single-lane alternating traffic will occur from 9 a.m. to 3 p.m. and 7 p.m. to 6 a.m. Monday through Friday, and possibly during weekends along Noblestown/East Main Street in Scott, Green Tree, Carnegie and Pittsburgh for road resurfacing. Crews from Lane Construction have begun work between the intersection of East Main Street and Washington Avenue in Carnegie and the intersection of Noblestown and Poplar Street in Green Tree. The project is scheduled to be completed in early August.

Advertise with us

Red Line, Beechview — Section of the Red Line of Port Authority light-rail system that runs through Beechview is closed as part of a T reconstruction project. The Port Authority is replacing rails embedded in Broadway Avenue between Potomac and Fallowfield avenues, which will affect about 12,000 commuters who use the Red Line to get to Downtown and other locations.

The Red Line will operate as normal from Fallowfield to Downtown and the North Shore. To accommodate passengers from other parts of Beechview and the South Hills, Port Authority has offered several options.

▪ In the construction zone, a free shuttle bus will run every 12 minutes during rush hours (6-9 a.m. and 4-6:30 p.m.) and every 30 minutes during other service hours.

▪ A free rail shuttle will run from Potomac to the Blue Line at Overbrook every 12 minutes in rush hours, every 20 minutes during the day and every 30 minutes in the evening.

▪ A temporary bus route, 42 Dormont, will run between the Mt. Lebanon station and Downtown via West Liberty Avenue during weekday rush hours.

Advertise with us

The contractor hired for the project will work Monday through Saturday, from 6 a.m. to 11 p.m.

Interstate 70 — PennDOT has seven projects under way on the 32-mile stretch of Interstate 70 between Eighty Four in Washington County and New Stanton in Westmoreland County. The I-70 work is part of a multi-year series of projects to upgrade the highway. Traffic near the 1-70/​Route 19 interchange moved to the eastbound lane with two lanes in each direction.

Smithfield Street, Downtown — Northbound travel lane and parking lane closed from Fourth to Fifth avenues for the reconstruction of the Forbes Avenue and Smithfield Street intersection. The closure is expected to last through the summer.