After months of planning and community meetings, Port Authority on Sunday will close part of the Red Line of the T system that runs through Beechview.
That means 12,000 South Hills riders who use that system to go to Downtown Pittsburgh or the North Shore will have to find an alternative. And it means businesses along Broadway Avenue in Beechview will find out whether they will continue to be viable with the help of accommodations Port Authority has made to lessen the effects of the project.
Michael Facchiano Contracting Inc. will begin work Monday on the $8.4 million project to replace the tracks that run down the middle of Broadway between Fallowfield and Potomac avenues. Beechview is the only place on the T where above-ground tracks run down the middle of a street.
Long-time Beechview residents have been concerned about the project because they know the neighborhood’s history: When Port Authority replaced the tracks in a two-year project that began in 1998, the business district suffered and the former Foodland supermarket never recovered and eventually closed. That’s why residents and the business community lobbied for the work to be done in one construction season this time with street closings occurring in phases to minimize disruption.
“For sure, the Port Authority has come a long way for helping everyone get through this,” said Phyllis DiDiano, president of Beechview Area Concerned Citizens. “I do think there will be less impact for commuters this time around.”
Facchiano will begin construction starting with the two ends of the street, where most of the businesses are located. Then workers will move to the middle, a mostly residential area.
That way, parking restrictions should last three months or less in each section.
Port Authority also has mailed fliers about the project to every home in the neighborhood and met with individual businesses, such as the IGA supermarket that replaced Foodland, to make sure supply trucks can reach them. In addition, there will be four crossovers for pedestrians to get from one side of Broadway to the other, two of which also will accommodate vehicles.
The contractor also will have financial incentives to get work done sooner, and the city has allowed the contractor to work Monday through Saturday from 6 a.m. to 11 p.m. instead of 7 a.m. to 9 p.m., with the last hour restricted to cleanup or preparation rather than actual construction.
The authority has an agreement with St. Catherine of Siena Catholic Church to make some parking available in its lot on weekdays. Traffic will be maintained in both directions throughout the project, but the only street parking in construction areas will be parallel parking on the outbound side.
The Red Line will operate as normal from Fallowfield to Downtown and the North Shore. To accommodate passengers from other parts of Beechview and the South Hills, Port Authority will have several options.
In the construction zone, a free shuttle bus will run every 12 minutes during rush hours (6-9 a.m. and 4-6:30 p.m.) and every 30 minutes during other service hours.
A free rail shuttle will run from Potomac to the Blue Line at Overbrook every 12 minutes in rush hours, every 20 minutes during the day and every 30 minutes in the evening.
And a temporary bus route, 42 Dormont, will run between the Mt. Lebanon station and Downtown via West Liberty Avenue during weekday rush hours.