In three different areas of Wildwood Road in Hampton, the roadway is sliding away under the road surface, so PennDOT will begin a year-long project in May to stabilize the road.

The road will be closed through November, reopen for the winter, and then close again next spring.

That work, expected to cost $1 million to $2 million, is among 50 new road and bridge projects totaling about $272 million that will begin this year in Allegheny, Beaver and Lawrence counties.

Wildwood Road has problems in three areas between Sylvan Drive and the Tuscan Inn, PennDOT spokesmen Steve Cowan said. Gabion walls, which the state Department of Transportation estimates were installed in the 1980s, are sliding and overturning, causing problems for the road surface.

Advertise with us

To correct the problem, crews will use soil nails to stabilize the gabions in the area between Sylvan Drive and Trillium Trail. Between Greenwood Drive and the Tuscan Inn, the slide will be repaired with a combination of a rock slope keyed in at the toe of the slope and a reinforced soil slope near the road.

Stabilization work is expected to continue through November. The road will reopen during the winter. Then in spring 2017, utility companies will have until April 15 to finish relocation work.

Once that is done, the construction crews will finish drainage work on the road and pave it.

Traffic will be detoured around the work area from Wildwood Road to Wildwood Sample Road to Sample Road to Mount Royal Boulevard to Route 8, then back to Wildwood Road.

Other work slated this year in PennDOT’s orange barrel parade include:

Advertise with us

• Finishing a $7.3 million project to replace three bridges on McKnight Road between Duncan Avenue and Route 19. Preparation work began this week for Monday’s closure of the ramp from Route 19 to McKnight Road for replacement of the final bridge. The ramp is expected to be closed for 32 days.

• A $2.48 million project to widen Pine Creek Road in McCandless to add a left-turn lane from Pine Creek for east-bound motorists to turn onto Route 19. The project, which will last until July 2017, also involves restoring a bridge.

• A $1 million to $2 million project to add a second left-turn lane from westbound Warrendale-Bayne Road to southbound Interstate 79 in Marshall and an additional left-turn lane from Warrendale-Bayne to Innovation Drive. Other work will include widening the I-79 ramp, improving signals and erecting new signs. The project will continue through 2017.

• A $4.6 million project to replace the Culmerville Truss Bridge over the Canadian National Railroad on Route 1028 in West Deer. The project will begin in April with single-lane alternating traffic during preparatory work. The bridge will be closed for 69 days for replacement, followed by additional periods of single-lane alternating traffic for finishing work. Work should be finished in October.

Other roads scheduled for milling and paving include:

Advertise with us

• Butler Logan Road from Thompson Run Road in McCandless to Mount Royal Boulevard in Hampton;

• East Ohio Street/Evergreen Avenue/Babcock Boulevard/Peoples Street/Evergreen Road from East Ohio Street in Millvale to McKnight Road in Pittsburgh;

• Ferguson Road from Thompson Run road in McCandless to Mount Royal Boulevard in Hampton;

• Babcock Boulevard from Westridge Road to Hemlock Drive in McCandless;

• Kleber Road/Butler Plank Road from Mount Royal Boulevard to Route 8 in Shaler.