Commuters who use the West End Circle will get a break for about two years once PennDOT finishes work on the long-delayed West Carson Street project in September.
In 2018, PennDOT expects to begin the next major project in that area: upgrading the one-mile section of Route 51 from the West End Circle to the Parkway West interchange and replacing the Shaler Street Bridge that carries Shaler Street above the highway on its way up Mount Washington. The project will be previewed at an open house from 5 to 7 tonight at the Mount Washington Healthy Active Living Center, 122 Virginia Ave., Mount Washington.
Project manager Bob Collins said the work will cost $10 million to $20 million, depending on whether the road needs to be completely rebuilt or can be upgraded by patching it and applying an overlay surface. The agency is testing and analyzing the existing surface to determine which level of work is required.
One lane of traffic will be maintained in each direction through most of the project, Mr. Collins said. There likely will be a couple of weekends with full closures during the bridge replacement.
One key element of the project will be lowering the road by 2-3 feet in the area of the Shaler Street Bridge. The bridge only has about 13 feet of clearance instead of the standard 16 feet, which has resulted in it regularly being struck by trucks, said Mr. Collins.
In addition, the bridge itself will be replaced using a process not often used in this area to reduce the amount of time Shaler Street will be closed. The 141-foot span will be assembled off site and rolled into place on the support columns, reducing closure from as long as four months to a couple of weeks, Mr. Collins said.
Shaler Street begins at Woodville Avenue and runs across Route 51 to Grandview Avenue.
Also, ramps to Wabash Street and the Parkway West will be upgraded. Mr. Collins said the deceleration lane to Wabash Street, where Minnotte Manufacturing Corp. is located, also will be extended to make it “a little less confusing.”
The overview of the new project comes as contractors finally have an end in site to the extended project to rebuild West Carson Street, which has caused massive traffic jams in that area. That $39 million project, delayed by more than a year by unexpected utility problems, should be finished in September after three years of work.
Ed Blazina: eblazina@post-gazette.com or 412-263-1470.