The southbound ramp from Route 19 to McKnight Road in McCandless will close for 32 days beginning Tuesday.

The PennDOT project will cause a significant detour for 10,000 motorists a day who use the ramp. It is the first of two major projects on McKnight Road scheduled this summer, the other being the installation of adaptive traffic signals to improve traffic flow through the area.

The bridge on the ramp from Route 19 to McKnight Road is the last of three bridges to be refurbished under a $7.3 million contract with Brayman Construction Corp. The ramp work will include deck replacement, steel repairs, bearing replacement and painting of the steel girders.

During the project, southbound traffic on Route 19 will continue past the closed ramp, turn left onto Pine Creek Road, bear right onto Blazier Drive and continue to McKnight Road.

Advertise with us

Additionally, left hand turns from Pine Creek Road to Route 19 will be prohibited. The detour for eastbound traffic on Pine Creek Road will send motorists through the intersection at Route 19 and have them bear right onto Blazier Drive and then left onto McKnight Road to northbound Route 19.

Westbound traffic on Pine Creek Road headed for southbound Route 19 will continue through the intersection at Route 19, turn left on Brandt School Road and left on West Ingomar Road to Route 19.

Another part of the project began last week with a long-term, single-lane restriction on northbound Route 19 between Ingomar Road and the northbound McKnight Road ramp to northbound Route 19. Crews will perform overhead bridge reconstruction through late May.

Later in the year, PennDOT will begin installing cameras and computers at 11 intersections over 9.1 miles of the highway between Evergreen Road and Peebles Road. The system, known as InSync and manufactured by Rhythm Engineering of Lenexa, Kan., adjusts lights based on the actual traffic on the main road and side streets an any particular time.

The system, recently installed on Route 22 in Monroeville and Murrysville, is expected to cost $500,000 to $1 million. Construction will be done in the fall with little effect on traffic, and the system will be tested and calibrated before it begins operation in late October.