Spring has sprung, so it’s time for PennDOT’s annual orange barrel parade. Here are road and bridge projects scheduled this year in the western suburbs:
• Finishing the $19 million project to reconstruct Route 50 from the Washington County line to Millers Run Road in South Fayette.
• Finishing the $9 million project to resurface Route 60 (Steubenville Pike) in Robinson between the Parkway West and Interstate 79 and the adjacent section of Route 22 from the Tonidale Bridge to the Parkway West, plus repairs to several bridges. Remaining work, including joint sealing and final pavement marking installation, should be finished in May.
• Finishing the $1.46 million project to replace the bridge that carries Washington Pike over Coal run near Bursca Drive in South Fayette. Traffic will be maintained during the work, which will be finished in September, but large trucks are being detoured.
• Finishing a $1.69 million project to reconstruct the drainage system at the former Aliquippa Tin Mill on Route 51 in Aliquippa. Woodlawn Road traffic will be detoured until the project is complete in late May.
• $9 million to $10.5 million to upgrade Route 22 between the Oakdale interchange and the Washington County line in North Fayette. The proejct will include concrete rehabilitation and patching, bridge preservation, guiderail and drainage updates, shoulder resurfacing, new signs, and pavement markings. The work, which begins in May and will last until late November, will involve long-term, single-lane restrictions on Route 22 as well as closures at the Noblestown interchange ramps and on a portion of Potato Garden Road.
• $4 million to $5 million to reconstruct and patch Route 51 in Coraopolis beginning in late April. The work will be done between Thorns Run Road and Barn Street on the Fifth Avenue section of Route 51 and between Thorns Street and Thorns Run Road on the Fourth Avenue segment. The project should be finished in December.
• $1 million to $2 million to replace the Noblestown Road bridge over Scotts Run in Collier. Work is expected to begin in late July and traffic will be detoured until the bridge is finished in mid-October. Additional work to replace a wall, resurface the road and improve drainage and guiderails will continue until December.
• $20.2 million to repave Route 65 from Crows Run Road in Conway to Route 18 in Rochester. Work beginning in April also will include drainage and guiderail updates, bridge and retaining wall preservation, and signal improvements. One lane of traffic will be maintained throughout the project, but ramps will be closed. The project continues until August 2017.
• $15.9 million to rehabilitate the Vanport Bridge that carries Interstate 376 over the Ohio River between Vanport and Potter. The project, which began last month, involves painting the bridge, a deck overlay, new bearings, dam replacements, and lighting and electrical upgrades. Traffic will be one lane in each direction through October 2017.
• $9.2 million to rehabilitate, patch and pave Kennedy Avenue in Aliquippa between Brodhead and Monaca roads. Work will begin this month and reduce traffic to one lane in each direction until the project is finished in December.
• $2.8 million to realign 1.25 miles of Smiths Ferry Road in Ohioville to shift traffic away from slide areas. The project will begin in late spring and he road will be closed until it is finished in November.
• $1 million to $2 million to replace a bridge over Little Mill Creek on Route 30 in Greene Township. The project, expected to begin in mid summer, also will relocate an unnamed tributary. The project will be finished in the fall.
• $1.95 million to replace the Route 251 bridge over Brush Run in South Beaver. Crews will work on one half of the bridge at a time beginning later this month. A temporary signal will control traffic. There also will be work at the intersection at Watts Mills Road. Work will be done in October.
• $1.6 million to replace the Anderson Road bridge over Small Run in Darlington and the Blockhouse Run Road bridge over Blockhouse Run in Daugherty.The Anderson project will be from July to late September and the Blockhouse work will be from May through August. Traffic will be detoured for both projects.
• $1.7 million to replace the Tulip Drive bridge over Brush Creek in New Sewickley. Work will begin in the spring and should be finished by mid October.
• $720,000 to replace the Reno Street bridge over Lacock Run in Rochester. A full closure and detour will be in place throughout the project, which will start in the spring and be finished by late August.
Other scheduled paving projects:
• Route 60 from Steuben Street in Crafton to Lorish Road in Robinson.
• Route 18 from Winford Lane in Raccoon to Old Frankfort Road in Potter.
• Route 68 from Private Drive to Huron Avenue in Industry.
• Route 588 from Carrs Lane in North Sewickley to Hartzell School Road in Marion.
• Route 251 from Darlington Road to Shenango Road in Chippewa.
• Darlington Road from Shenango Road to Constitution Boulevard in Chippewa.
Ed Blazina: eblazina@post-gazette.com or 412-263-1470.