Anyone from the South Hills who wants to get to Downtown Pittsburgh during the upcoming road construction season is advised to start early. Now wouldn’t be a bad idea.

The Parkway West and the Smithfield Street Bridge will be open without restrictions, but just about every other artery from the south will be under construction — the Liberty Bridge (and the Route 51-West Liberty Avenue interchange approaching the Liberty Tunnel that joins the bridge), the Philip Murray (10th Street) from East Carson Street to Second Avenue, the Birmingham Bridge between East Carson Street and Oakland and the interchange at the end of the Glenwood Bridge in Hays. All of those bridges cross the Monongahela River and provide access to the Downtown area.

The most significant — and likely most disruptive — project is expected to be the $80 million rehabilitation of the Liberty Bridge, often cited as the poster child of bad bridges when officials were lobbying for a new state transportation funding bill in 2014. Opened in 1928, the bridge was last rehabbed in 1986 and has a 30-ton weight limit.

PennDOT began preparation work for the project last year with extensive testing to determine the underlying condition of the bridge. Next is two years’ worth of deck and understructure replacement that will cause major traffic problems beginning next month.

Advertise with us

PennDOT officials Wednesday detailed that project and others that will take place this year. Overall, the agency expects to begin 50 projects in Allegheny, Beaver and Lawrence counties this year at a total estimated cost of $276 million.

Although the Philip Murray Bridge is an Allegheny County project, PennDOT District Executive Dan Cessna said the long-ignored condition of bridges across the state has left officials with little choice than to begin projects at the same time now that money is available. The county expects to begin a three-year rehab of that bridge, including replacing the deck, repairing abutments and painting, some time this season.

“There’s a lot of work crossing the Monongahela River,” Mr. Cessna said. “That’s the challenge with aging infrastructure. We don’t have five years left to wait on some of these projects.”

That’s part of the reason why PennDOT put contractors on overdrive — working overnights with frequent full weekend closures the past two summers — to finish upgrades to the Parkway West between Interstate 79 and the Fort Pitt Tunnel. Upgrades to the tunnel itself are almost finished, too.

“We wouldn’t want that [Parkway West and tunnel work] going on at the same time as all of this bridge work,” Mr. Cessna said.

Advertise with us

Mr. Cessna said PennDOT chose to upgrade the Route 51-West Liberty Avenue interchange at the approach to the Liberty Tunnel at the same time as the Liberty Bridge work in hopes that motorists already will be avoiding the area. That $2 million-$5 million project, scheduled to begin in June, involves new asphalt on Route 51 and West Liberty as well as rehabilitating two bridges and ramps on Route 51.

Ramps are expected to be closed for two weeks each.

“Certainly [Route 51 work] will add to concerns for motorists in that area,” Mr. Cessna said.

Liberty Bridge traffic will be restricted throughout the remainder of the project. This year, that will mean two lanes inbound and one outbound in the morning; at 2 p.m. daily, that will reverse with two lanes outbound and one inbound for the evening rush hour. There will be no outbound right-turn-only lane to Mount Washington.

From 8 p.m to 5 a.m., traffic will be limited to one lane in each direction. The restrictions will be adjusted for major events in Pittsburgh such as playoff hockey games, Pirates games, stadium concerts and Steelers games.

Advertise with us

There also will be long-term closures of the ramps to and from the bridge to the Boulevard of the Allies.

The restrictions only get more onerous in 2017, when there will be full bridge closures on five weekends and 26 overnight closures. In addition, the Boulevard of the Allies near the bridge will be closed for 80 days next year.

Other major projects:

• $20 million-$30 million for a two-year project to repair the bridge ramps and road surface on Route 65 between the Fort Duquesne Bridge and the McKees Rocks Bridge on the North Side. The work, which begins in May, will be coordinated with stadium events.

Mr. Cessna called this “a section of road that really needs attention.” The work involves paving, bridge rehabilitation, drainage and guiderail updates, new signs and retaining wall repairs with long-term single-lane closures and nightly and weekend ramp closures expected.

Advertise with us

Two lanes of traffic in each direction will be available between the Fort Duquesne and West End bridges and one lane each way between the West End and McKees Rocks bridges.

• $12.74 million for work beginning this month to reconstruct the roadway and ramps from East Ohio Street to Route 28. That will involve a 45-day closure of the southbound ramp from Route 28 to East Ohio, followed by a 64-day closure of the northbound ramp from East Ohio to Route 28.

Beginning in May, East Ohio will be reduced to one lane in each direction for 145 days. There also will be five weekend closures of Route 28 for crews to paint bridges.

• $66.3 million to rebuild about 7.5 miles of the Parkway West near Pittsburgh International Airport from McClaren Road to just across the Beaver County line. There will be lane shifts, but traffic will be maintained throughout the project.

• $27 million-$30 million for a three-year project to upgrade and realign Freedom Road in Beaver County from Route 65 in Conway to Park Quarry Road in New Sewickley. The road is a major connection between Route 65 and Route 19 in Cranberry.

Advertise with us

• $10 million-$12 million for a two-year project to rehabilitate the Mahoning Viaduct that carries Route 18 over the Shenango River between New Castle and North Beaver.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.