PennDOT expects this summer to begin the last leg of rebuilding Interstate 70 between the interchanges it shares with I-79 in Washington County, a three-year project expected to cost more than $100 million.

The new project involves rebuilding 6.5 miles of I-70 between Beau Street in South Strabane and Route 519 in Eighty Four. It will dovetail with a $50 million project to widen and rebuild the highway from the North Junction with I-79 to Beau Street, which is expected to be finished in June 2017.

Plans for the project will be on display from 5 to 7 p.m. Wednesday at the South Strabane Fire Station No. 2 at 172 Oak Springs Road. Project managers with the state Department of Transportation will make a short presentation at 5:30 p.m. and be available to answer questions after that.

Barry Lyons, one of two project managers, said the work is broken into two segments, about 3 miles from Beau Street to the South Junction of I-79, and 3.5 miles from South Junction to Route 519.

Advertise with us

The first section, technically I-79/​I-70, will be widened by 32 feet to add a third lane in each direction. The outside berm will be increased from 10 feet to 12 feet and the inside shoulder will increase from 4 feet to 10 feet.

In addition, entrance and exit lanes will be longer to allow safer merges and sound barrier walls ranging from 11 to 15 feet high will be built along a 2,100-foot section.

In the second section, the two existing lanes will be rebuilt, the shoulder expanded from 10 feet to 12 feet and the median widened from 2 feet to 10 feet. Entrance and exit lanes will be extended, a retaining wall will be built and three culverts will be widened.

The biggest aspect of this section of the work will be relocating about 2,600 feet of a tributary to Little Chartiers Creek. That will allow crews to relocate the road to soften a sharp bend, said Troy Pritts, the other project manager.

Throughout the project area, the road will be rebuilt from the base up because most of it is from the original construction in the 1950s, Mr. Lyons said. Crews also will upgrade all drainage facilities and other utilities.

Advertise with us

PennDOT plans to keep two lanes of traffic open during the day at all times, but it is likely there will be overnight lane closures between 8 p.m. and 6 a.m.

“It takes a lot of work to keep the two lanes open, but that’s what we have to do because of the amount of traffic in the area,” Mr. Lyons said.

At a cost of more than $100 million, the work will be the most expensive project ever in PennDOT District 12, which includes Washington, Westmoreland, Fayette and Greene counties.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.