The Parkway East reopened Thursday just in time to channel New Year’s revelers into Downtown, delighting city officials who had worried for months over the days-long closure.

Inbound traffic resumed at 2 p.m., while outbound traffic was set to restart by midnight. General contractor Mosites Construction & Development Co. had until 6 a.m. today to clear the highway after the Greenfield Bridge was imploded Monday.

“We pushed hard on the contractor, and they did a fantastic job,” said Guy Costa, chief operations officer for the city.

He said he had hoped for a parkway reopening by New Year’s Eve, when thousands of people head Downtown for Highmark First Night Pittsburgh events. Clear weather Thursday night guaranteed a large turnout for the 22nd annual celebration, produced by the Pittsburgh Cultural Trust.

Advertise with us

Parkway access probably helped attendance, too, said Shaunda Miles, a spokeswoman for the nonprofit trust.

“You want as few challenges as possible. If that was one less reason for people to decide to stay in, and one more impetus for people to make their way down with greater ease, we’re really pleased,” Ms. Miles said.

Robinson-based Mosites has a $17.5 million contract with the city to remove and replace the 94-year-old Greenfield Bridge, which connected Greenfield with Schenley Park above the parkway. Detours since Sunday rerouted the highway traffic through Wilkinsburg, the East End and Oakland.

Mosites project manager Derrick Jeannerette said detailed preparations helped to keep the work on schedule.

“I think everything went somewhat as expected, if you can expect anything on this type of job,” he said. “I don’t think we ran into too many issues.”

Advertise with us

Demolished concrete columns from the bridge’s north end slid onto the roadway, saving a lot of cleanup time, said Patrick Hassett, the city’s assistant director of public works. Otherwise, he said, workers would have had to scale a hillside to remove that debris.

“A lot of the debris was in small enough chunks that it didn’t have to be cut up and could easily be removed,” Mr. Hassett said.

Some rubble landed outside a 5-foot-high dirt cushion, he said, causing cracks in the road pavement and perhaps a couple of dozen potholes on the parkway’s outbound side. He said a shoulder area there showed signs of collapse.

Mosites is responsible for fixing up the site, and initial repairs kept the outbound lanes from reopening sooner, according to city officials. They expect that the parkway — part of Interstate 376 — will close again over a couple weekends in 2016 as workers install steel for the replacement bridge, Mr. Hassett said.

Mr. Costa said that should happen in late autumn. He said the new span could open to traffic in summer 2017.

Adam Smeltz: asmeltz@post-gazette.com or 412-263-2625. Twitter @asmeltz.