This weekend’s closure of the Parkway West and the Pittsburgh Steelers’ game Sunday night combined to postpone the expected closure of the Parkway East Saturday and Sunday.
Instead, Pittsburgh officials said the Parkway East will be closed from 11 p.m. Dec. 11 through 6 a.m. Dec. 14, giving Mosites Heavy Construction about 13 more hours to do preparation work for demolition of the Greenfield Bridge that runs above the highway. If the work had been done this weekend, the highway was scheduled to open at 5 p.m. Sunday to accommodate traffic for the football game.
In addition, PennDOT scheduled paving on the Parkway West for this weekend as well, meaning two of the main arteries into the city would have been closed for long periods of time.
“This is in the best interests of the public and the contractor,” said city spokeswoman Katie O’Malley. “Next weekend the contractor will have a full weekend closure. Having more hours for work next weekend is beneficial.”
The bridge project is on a tight schedule for demolition during the week between Christmas and New Year’s Day because those days have the least traffic all year and it is the only time PennDOT will allow the highway to be closed for an extended period. If the bridge isn’t ready to come down then, demolition would be delayed until Christmas week next year.
PennDOT spokesman Steve Cowan said motorists who use the Parkway West should be free from major traffic restrictions for construction work after this weekend.
If weather permits paving Friday and Saturday, he said, the Carnegie interchange will reopen and the most disruptive work during the two-year, $72.8 million project will be finished. The highway likely will close between Interstate 79 and the Fort Pitt Tunnel for one weekend in the spring for final paving work, which can’t be done until the weather is warmer.
Some shoulder work also may be done in the spring but that shouldn’t cause traffic restrictions.
PennDOT also doesn’t expect any more weekend closures this year of the Fort Pitt Tunnel. The tunnel is undergoing rehabilitation under a separate contract, but a lot of the closures have been coordinated with Parkway West work.
This weekend’s work will close the parkway inbound from I-79 to Parkway Center Drive from 9 p.m. Friday to 6 p.m. Saturday. The parkway will be closed outbound between the Greentree/Crafton exit and I-79 from 6 a.m. to 4 p.m. Sunday.
When Swank Construction Co. finishes the work this weekend, the highway will return to its original configuration. Mr. Cowan said there will be additional overnight closures through Christmas as crews conduct grinding operations on bridge decks in the Carnegie area.
The project included resurfacing 5.22 miles of highway in both directions between I-79 and the Fort Pitt Tunnel, repairing 14 bridges and 17 signs and reconstructing median strips, shoulders and ramps.
Ed Blazina: eblazina@post-gazette.com or 412-263-1470.