Lane and shoulder restrictions will be in place on Route 28 in both directions in O’Hara and Harmar starting today so signs can be installed.

PennDOT said the restrictions will occur from 10 a.m. to 3 p.m. weekdays between the RIDC Drive (Exit 10) interchange in O’Hara and the Russellton Road overpass in Harmar.

Crews from Wellington Power Corp. will be installing the signage through Dec. 11.

Also, the planned closure of the Parkway East this weekend has been moved back one week. The closures will now take place from 11 p.m., Dec. 11 through 6 a.m., Dec. 14.

Advertise with us

The highway will close so crews can prepare for the Greenfield Bridge implosion. The outbound/eastbound side of the parkway will be closed from Oakland to Squirrel Hill/Homestead. The inbound/westbound side will be closed from Wilkinsburg/Forest Hills to Oakland.

Shoppers are reminded that parking is free every Saturday through Dec. 22 in Downtown Pittsburgh at the dozen or so garages operated by the Pittsburgh Parking Authority.

Traffic restrictions:

Parkway West/I-376 -- Last major weekend closure Friday and Saturday for paving between Greentree and Interstate 79. Inbound from I-79 to Parkway Center drive from 9 p.m. Friday to 6 p.m. Saturday. The parkway will be closed outbound between the Greentree/Crafton exit and I-79 from 9 p.m. Saturday to 4 p.m. Sunday. Also Parkway West closed overnight Thursday. A detour will be posted.

Fort Pitt Tunnel -- Overnight closures in the outbound (westbound) Fort Pitt Tunnel 9 p.m. to 6 a.m., Monday through Friday nights through Dec. 4 for concrete repairs.

Advertise with us

Corliss Tunnel -- Traffic from southbound Route 51 (West Carson Street) will be unable to access the Corliss Tunnel around-the-clock today through Dec. 16. Detours will be posted.

Route 50/Noblestown Road --  Single-lane alternating traffic will occur between Mansfield Avenue and Durbin Street for curb and drainage work, weekdays from 9 a.m. to 3 p.m. through Dec. 22.

Mt. Lebanon Boulevard -- Single-lane alternating traffic weekdays, 7 a.m. to 4 p.m. through Dec. 16 between Washington Road/Route 19 and Castle Shannon Boulevard.

Hulton Bridge -- Motorists are reminded that the recently opened Hulton Bridge, which connects Oakmont to Harmar over the Allegheny River, will maintain a lane restriction through the spring to construct the final wing wall of the new bridge after the old bridge is demolished in mid-January.

Wabash tunnel -- All vehicles can use the tunnel through August 2016.

Advertise with us

Second Avenue -- Single-lane restrictions weekdays from 9 a.m. to 3 p.m. on Second Avenue between Municipal Court Drive and Try Street through Dec. 11 as crews continue survey work on the Liberty Bridge.

Greenfield Bridge -- Closed for two years while a new span is constructed over the Parkway East/Interstate 376. The bridge, which connects Alger Street in Greenfield with Schenley Park, will be imploded on the parkway in late December to make way for the $17.5 million construction project. The parkway will be closed for five days between Christmas and New Year’s Day. Detours are posted and can also be found, along with a construction schedule, on the Greenfield Bridge Project website of the Oakland Transportation Management Association.

Birmingham Bridge -- Single-lane restrictions periodically throughout the winter in each direction of the bridge. At least two lanes will be maintained in each direction through the end of February.

Smithfield Street, Downtown -- The portion of the street between Fourth and Fifth avenues open for time being. Then seven-month closure resumes for reconstruction of the Forbes Avenue and Smithfield intersection. A northbound lane and parking lane will be closed from Fourth to Fifth avenues. The southbound bus-only lane will remain open to accommodate the Port Authority bus schedules.

Route 286/Golden Mile Highway, Monroeville -- Overnight ramp closures at Route 22 will close at 10 p.m. weekdays and Saturdays through Sunday, reopening by 6 a.m. daily. Ramp traffic detoured via Alpine Village Drive.

Advertise with us

Homestead-Duquesne Road, Munhall -- Closed for slope stabilization project at the Franklin Bend near Vondera Street. Completion expected mid-December.

Brightwood Road, Bethel Park -- Paving causing lane closures with flaggers directing traffic from 7 a.m. to 6 p.m. weekdays until further notice.

Fall Run Road, Shaler -- Closed indefinitely between Maple Street and Middle Road. Those who live along the roadway will be able to access their homes from Middle Road.

Route 51/West Carson Street -- Closed to outbound traffic. Estimated completion June 2016.

Route 8, Hampton -- Northbound lane closed between Clearview Road and Murray Avenue through mid-December.