The Parkway East will close next weekend to prepare for the Greenfield Bridge implosion. The outbound/eastbound side of the parkway will be closed from Oakland to Squirrel Hill/Homestead. The inbound/westbound side will be closed from Wilkinsburg/Forest Hills to Oakland. Detours will be posted.

The weekend closure is set to begin at 10 p.m. on Friday, Dec. 4, and run through 5 p.m. Sunday, Dec. 6.

More details can be found here.

Also, an earlier crash on the Parkway West this morning near the Carnegie exit westbound has been cleared. The crash was reported shortly after 7 a.m. and was cleared by 9, according to PennDOT.

Advertise with us

Shoppers are reminded that parking is free every Saturday through Dec. 22 in Downtown Pittsburgh at the dozen or so garages operated by the Pittsburgh Parking Authority.

Traffic restrictions:

Mt. Lebanon Boulevard -- Single-lane alternating traffic weekdays, 7 a.m. to 4 p.m. through Dec. 16 between Washington Road/Route 19 and Castle Shannon Boulevard.

Hulton Bridge -- Motorists are reminded that the recently opened Hulton Bridge, which connects Oakmont to Harmar over the Allegheny River, will maintain a lane restriction through the spring to construct the final wing wall of the new bridge after the old bridge is demolished in mid-January.

Wabash tunnel -- All vehicles can use the roadway through August 2016.

Advertise with us

Greenfield Bridge -- Closed for two years while a new span is constructed over the Parkway East/Interstate 376. The bridge, which connects Alger Street in Greenfield with Schenley Park, will be imploded on the parkway in late December to make way for the $17.5 million construction project. The parkway will be closed for five days between Christmas and New Year’s Day. Detours are posted and can also be found, along with a construction schedule, on the Greenfield Bridge Project website of the Oakland Transportation Management Association.

Birmingham Bridge -- Single-lane restrictions periodically throughout the winter in each direction of the bridge. At least two lanes will be maintained in each direction through the end of February.

Smithfield Street, Downtown -- The portion of the street between Fourth and Fifth avenues open for time being. Then seven-month closure resumes for reconstruction of the Forbes Avenue and Smithfield intersection. A northbound lane and parking lane will be closed from Fourth to Fifth avenues. The southbound bus-only lane will remain open to accommodate the Port Authority bus schedules.

Route 286/Golden Mile Highway, Monroeville -- Overnight ramp closures at Route 22 will close at 10 p.m. weekdays and Saturdays through Sunday, reopening by 6 a.m. daily. Ramp traffic detoured via Alpine Village Drive.

Homestead-Duquesne Road, Munhall -- Closed for slope stabilization project at the Franklin Bend near Vondera Street. Completion expected mid-December.

Advertise with us

Brightwood Road, Bethel Park -- Paving causing lane closures with flaggers directing traffic from 7 a.m. to 6 p.m. weekdays until further notice.

Fall Run Road, Shaler -- Closed indefinitely between Maple Street and Middle Road. Those who live along the roadway will be able to access their homes from Middle Road.

Route 51/West Carson Street -- Closed to outbound traffic. Estimated completion June 2016.

Route 8, Hampton -- Northbound lane closed between Clearview Road and Murray Avenue through mid-December.