A week after PennDOT created an even bigger inbound traffic jam at the West End Circle, officials are looking at changes to ease morning rush-hour traffic on West Carson Street.
The changes include opening the Corliss Tunnel to inbound traffic from West Carson and encouraging the contractor to finish the work in less than one month.
The latest problem in the $39 million project to rebuild West Carson Street through the West End Circle to the South Side began on election day, when crews closed the portion of West Carson that goes under the circle. That forced all traffic — limited to one lane inbound but offering an option there to go under or through the circle — to use the already-congested circle.
As a result, drivers reported delays of 45 minutes or more last week.
“We are putting all of the traffic into a very congested corridor at the West End Circle,” said PennDOT spokesman Steve Cowan.
To help east the traffic jam, PennDOT on Friday opened the Corliss Tunnel, which is a right-hand turn off West Carson. Police officers may be added to help move traffic and PennDOT would like contractor Lane Construction to complete that part of the project before the scheduled Dec. 3 finish.
Read More
Throughout the project, West Carson has been closed to outbound traffic but one inbound lane has remained open in the morning.
The traffic situation is the latest problem PennDOT has encountered in the project, which was scheduled to be finished in September after two years of work. But contractors ran into problems with utility lines that halted road work for more than six months and pushing the completion date back until late spring.
“We are back to making progress,” Mr. Cowan said. “Road work is being done now.”
Ed Blazina: eblazina@post-gazette.com or 412-263-1470.