If Mother Nature allows preparatory work to be completed the next two days, the Birmingham Bridge will reopen Friday to full traffic in both directions for the winter.

The preparation work will involve restricting traffic to one southbound lane and one northbound lane from 10 a.m. to 3 p.m. Wednesday. That will allow crews to make pothole repairs and other preparations for reopening.

On Thursday, all of the northbound lanes that have been closed for rehabilitation will be open, but only one southbound lane will be open from 9 a.m. to 3 p.m.

If that work is completed, all lanes of the bridge between South Side and Oakland will be open Friday morning. PennDOT expects to have single-lane closures periodically throughout the winter.

Advertise with us

The full project will resume in March, when all traffic will be moved to the northbound lanes so the southbound side can be rehabilitated.

This work is part of the $28.5 million project that includes painting the entire superstructure, steel repairs, bearing replacements, substructure repairs, light pole replacements and a concrete overlay.

The project should be finished in spring 2017.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.