The new Hulton Bridge that will open Oct. 20 will be more than twice as wide as its predecessor, with twice as many lanes and a price tag more than 200 times that of the old span.

“It’s a huge improvement to this area,” state Transportation Secretary Leslie Richards said at a ceremony Thursday to announce the opening date. “The new Hulton Bridge is another milestone on our journey to a better tomorrow.”

The old bridge, with narrow lanes, a lilac paint job that has given way to a patina of rust and a designation as structurally deficient, will close Oct. 5 to allow the contractor, Brayman Construction of Saxonburg, to align the roads on both ends with the new span.

The detours will be long, as the bridge’s nearest neighbors (aside from the Pennsylvania Turnpike crossing) are the C.L. Schmitt Bridge in New Kensington, about seven miles away, and the Highland Park Bridge in Pittsburgh, six miles away via Freeport Road and eight miles away via Allegheny River Boulevard. A previous two-week closure occurred in June.

Advertise with us

Ms. Richards clicked off the improvements that the $65.7 million new bridge will offer: four 11-foot-wide lanes (vs. two 10 1/2 foot lanes on the old bridge); a four-foot-wide median (vs. none on the old bridge); six-foot-wide shoulders (vs. none) and a five-foot concrete walkway (vs. a steel grate sidewalk).

Two left turn lanes will carry traffic onto the bridge from southbound Freeport Road. At the Oakmont side, two eastbound lanes will extend from the bridge to Allegheny Avenue.

The new span is 69 feet wide, more than double the 32-foot width of the old structure.

The old bridge, built in 1908 at a cost of $306,000, “has served as an important link for nearly 26,000 vehicles every single day,” Ms. Richards said. It will be imploded sometime next year.

Dan Cessna, PennDOT district executive, said the new bridge will reduce travel times by 20 to 40 percent.

Advertise with us

Construction began in 2013 after years of efforts to fund the project. The schedule was designed to have the new bridge in place for the U.S. Open golf tournament that will be played at Oakmont Country Club next June.

“This is crucial to the future of the Allegheny Valley,” said state Rep. Frank Dermody, D-Oakmont, who pushed for the new bridge shortly after being elected to his first term in 1990. “It’s going to make a huge difference in the lives of the people of the Allegheny Valley.”

Jon Schmitz: jschmitz@post-gazette.com or 412-263-1868. Twitter: @pgtraffic.