A $15.9 million resurfacing and improvement project on Route 51 from Lebanon Church Road to the Liberty Tunnels began this week, the Pennsylvania Department of Transportation announced.

The initial restrictions will occur between the tunnels and Route 88, with single-lane traffic in both directions from 9 a.m. to 3 p.m. weekdays, weather permitting. Overnight work will restrict traffic to one lane both ways from 9 p.m. to 8 a.m. southbound and 7 p.m. to 6 a.m. northbound. The restrictions will continue into late July.

Weekend lane restrictions will be announced later in the project, which is scheduled for completion next June. No restrictions are planned during peak travel hours.

A water main replacement project also began Monday, causing overnight restrictions between St. Norbert Street and Overbrook Boulevard from 7 p.m. weekdays until 5 a.m. through June 30.