The Glenwood Bridge, which opened in 1966, is Pennsylvania’s first all-welded steel truss bridge and offers a back-door route to Downtown Pittsburgh for South Hills motorists. The four-lane span, which cost $18 million, links Glenwood and Hazelwood with Hays, a neighborhood in the 31st Ward.
The bridge is named for a neighborhood bounded by Glenwood Avenue, Second Avenue, Johnston Avenue and the Monongahela River. Glenwood derived half of its name from the Woods family, which included George Woods Jr., Pittsburgh’s first surveyor.
He was a descendant of Irish immigrant George Woods, who made his fortune trading with the Indians in the late 1700s and settled on a 530-acre farm then known as Scotch Bottom, now Glenwood. The Glen came from the Glen Hotel, a neighborhood landmark. In the 19th century Glenwood thrived with boat building, and in the 20th century it had a Jones & Laughlin steel mill.
When construction began in August 1960, the Pittsburgh Pirates were winning the National League pennant and went on to win the World Series.
Six miles from the Point and five miles east of Downtown, the new Glenwood Bridge has 6,830 tons of structural steel and is 2,276 feet long. During construction, more than 1 million tons of earth were removed from two large hillsides in Hays.
The earlier version of this bridge was a 70-year-old, rickety, two-lane affair with a wooden deck that was so badly torn up it caused blowouts in motorists’ tires. Trolley tracks were removed from the deck in 1964 and new timber flooring was installed. Entrance signs warned motorists not to throw lighted cigarettes on the wooden bridge.
In the summer of 1964, Hazelwood residents fed up with the bridge’s poor condition and delays in building the new bridge staged a three-day protest. They set up barricades and staffed them around the clock. The bridge was closed from midsummer until November.
By that time, the state was planning ramps for the new bridge and negotiating agreements with four rail companies to remove tracks and overhead crossings.
Contracts were finally signed with the Pennsylvania, Baltimore & Ohio and Pittsburgh & Lake Erie railroads and Pittsburgh Railways Co. and work proceeded.
The new bridge opened to traffic in 1966 and was dedicated on Dec. 20, 1968. In July 1969, the old wooden bridge finally came down.