Like it or not, summer visitors who drive Interstate 70 through Westmoreland County will have lots of time to see the countryside.

Online Graphic:
Interstate 70

See a graphic showing the next phase of Interstate 70 repaving.

A contractor working for the Pennsylvania Department of Transportation today plans to start rolling out orange-and-white barrels that will leave only one lane open in each direction for eight miles between the Speers Bridge over the Monongahela River and Smithton Bridge over the Youghiogheny River.

Advertise with us

PennDOT calls it "Phase 3."

"Phase 1" is already under way, a five-mile section between Madison and Youngwood, past the busy New Stanton Interchange of the Pennsylvania Turnpike.

But the contractor works only between 6 p.m. and 6 a.m., when traffic is light. Workers take down traffic control devices every morning in order to restore all lanes.

"Phase 2" is a four-mile section in the middle. It will be done last. In the meantime, it will act as a buffer zone for westbound traffic funneling into a one-lane queue to travel through the new Phase 3 work zone and for eastbound traffic emerging from the chute.

Restrictions in the eight-mile section will remain in place around-the-clock, probably through early August, said Scott Faieta, a PennDOT construction engineer overseeing the project.

Advertise with us

More than 40,000 vehicles a day use the stretch of I-70 through Westmoreland County in summer, most of them going to and from the turnpike.

The 17-mile project is costing $3.6 million, or slightly more than $200,000 a mile, compared to $1.5 million a mile that PennDOT is paying to resurface the Parkway West just west of Pittsburgh.

But PennDOT is milling off and repaving only the top 2 inches on I-70 rather than full-depth resurfacing being done on I-279.

" 'Pavement Preservation' is a new program for us," Faieta said. "It's designed to create a smooth, rideable surface and extend the life of the pavement at the same time.

"We're spending 100 percent state money on this," whereas the federal government typically pays from 50 to 90 percent of the share on the interstates.

Advertise with us

Most of the 17-mile stretch has already been rebuilt and-or resurfaced within the past 10 years.

Faieta said Phase 3 work will take place over a combination of shifts, 6 p.m. to 6 a.m., traditional daylight and on some weekends. State police are to assist at key points such as the Route 51 interchange from 6 to 9 a.m. and from 3 to 6 p.m. weekdays.

"Once the barrels go up this weekend, they'll stay up," Faieta said, because Phase 2 is to follow and take place through mid-September.