The long-delayed remediation of a contaminated Armstrong County site where nuclear fuel for submarines and reactors was produced in the 1960s could begin in 2023, according to a project timeline discussed at a U.S. Army Corps of Engineers public meeting Thursday.
Tim Herald, the corps’ project manager, told the 65 people who attended the meeting, held virtually online due to the pandemic, that the excavation work under a $350 million contract with Tennessee-based Jacobs Technology Inc. would likely continue through 2031.
“It’s been a long time coming, but we’re absolutely on board for getting after it,” said Col. Andrew Short, commander of the corps’ Pittsburgh District. “It’s great to see the project begin to move forward over the last 2½ years and we have a high confidence level we will have the money on an annual basis to keep the project going.”
Known as the “Shallow Land Disposal Area,” the 44-acre property, along the Kiskiminetas River in Apollo and Parks Township, about 30 miles northeast of Pittsburgh, contains an estimated 36,000 tons of uranium and plutonium waste buried in 10 trenches.
Residents of the area have expressed concern about potential cancer and other health problems caused by exposure to radioactivity on the site, though no one asked questions or expressed those concerns during the meeting.
The site initially was owned by Nuclear Materials and Equipment Corp., which operated the nuclear fuel plants. It was later sold to Babcock and Wilcox Co., which closed the facility in 1983. The corps is maintaining the site, conducting regular environmental monitoring and providing security.
Bill Frederick, a groundwater scientist with the corps’ Buffalo District, said there was no evidence of any migration of contaminants off the waste site in groundwater sampling in 2018 and 2019 from 24 monitoring wells and two surface locations.
Based on sampling done from 2003 through 2019, Mr. Frederick said the groundwater is not contaminated with radioactive material but the corps is monitoring volatile organic compounds related to the waste in the trenches.
He said he is awaiting lab results for groundwater sampling done in October.
Groundwater monitoring began in the 1990s and the corps did its first assessment of the site in March 2002.
It had to stop excavation and removal of the waste in the spring of 2012 when it discovered greater than expected amounts of weapons-grade uranium and plutonium in two of the 10 trenches. In March 2014, an investigative report by the Nuclear Regulatory Commission found there was more of the waste than previously known, and those findings complicated and further delayed the already long site-cleanup efforts.
In 2017, cleanup efforts were delayed yet again by a contract dispute, but Mr. Herald said the project is now “at or near the top of the corps’ priority list.”