Beaver County school districts will reconsider a loan to pay for renovations at New Horizon, a special education school, months after a handful of officials raised concerns about the price tag.
During a nonvoting meeting at the intermediate unit Tuesday, IU officials spent hours working with superintendents and school directors to reduce costs of the emergency project after mold and asbestos were found in the building last year.
The project cost could now total $14.8 million, a decrease of more than $1 million.
“We’re anxious to get this going and moving forward,” New Brighton Superintendent Joseph Guarino said.
School districts must now approve a resolution permitting the IU to take out a loan not exceeding $15 million. The loan will be paid by each of the member school districts. The IU board could vote on funding for New Horizon during its Jan. 28 meeting.
Beaver County commissioners on Tuesday also pledged $1 million to the project, which will be broken out over four years.
Mold was initially found at New Horizon at the end of the last school year. Since then, the school’s 177 students from kindergarten to age 22 have instead been using the former Midland Innovation + Technology School building.
But the space is nearly three times smaller than the school’s original space. That means up to three classrooms have been combined into one section, separated by shelves. Temporary changing areas and calming corners have also been constructed throughout the building.
Because of that, more than 70 people showed up in December, calling on the board to approve funding that would allow students to return to their original building next school year.
But at that meeting, IU directors removed two motions, one that would have allowed officials to move forward with work to resolve the mold and another that would have authorized a $16.5 million loan for the project. They cited the threat of potential litigation.
At the time, districts were asked to approve a resolution for a loan not to exceed $20 million.
But a handful questioned the cost. Some did not approve the resolution; others changed the not to exceed figure to a lower number.
On Tuesday, many in those districts said they supported the project and the mission of New Horizon. But they continued to question the scope of the project, its timeline and overall costs.
Those concerns — along with some saying their boards would not approve a resolution exceeding $15 million — were taken into consideration as a new resolution was crafted.
BVIU Executive Director Eric Rosendale added that the $20 million was “a cushion. It was never ever to be $20 million. It was a ‘what if something else needs to be done.’”
Other school leaders pointed to rising costs if they would have to find new placements for special education students other than New Horizon.
At Western Beaver, the district would need to send eight students to at least two different sites without New Horizon, something that would cost thousands of dollars in additional expenditures.
Thomas Moward, the Central Valley board representative, called the situation an “opportunity.”
“This is a bad situation that happened to a great place,” Mr. Moward said. “But instead of looking at it as something ill, let’s look at this as an opportunity to make this place viable for the next 50 years.”