The former Franklin Primary Center in Munhall stood quiet this week, an almost empty shell of what was once a bustling Steel Valley elementary school.
Hallways that formerly swarmed with excited students were still, the classrooms blank of posters and lessons. Sparse conference rooms gave few signs they were still in use, the only sounds echoing from the front of the building where a handful of administrators are still housed.
While plans are delayed, Franklin Primary Center will soon be demolished to make way for a new elementary school that will combine students in kindergarten through fourth grade who are currently split between Barrett Elementary in Homestead, built in 1934, and Park Elementary in Munhall, constructed in the early 1900s. The project, which is expected to be completed by 2027, could cost around $56 million.
“We have gotten to the point where the buildings we currently have are no longer adequate to our needs,” Michael Sullivan, Steel Valley’s director of facilities, said Monday. “At some point we had to make a move. The longer we wait the more we risk having something happen at the schools where we have a failure in a major system or something and then we’re out of school and we’re scrambling to get kids in place. It’s long overdue.”
Across the region many district administrators are pondering multi-million dollar school construction projects as they grapple with aging infrastructure that has reached the end of its lifespan or that have simply run out of room as an influx of children enroll in their districts.
In all, there are currently more than a dozen projects being considered in districts throughout Allegheny and Westmoreland counties.
Read More
Brentwood Borough
“This is an exciting time for our community,” Brentwood Borough School District Superintendent Amy Burch said. “We haven’t had anything new built here since the early 90s and even though the buildings were meticulously maintained for over 100 years, it’s time. It’s time to move forward. We want this school to be a beacon for new families to move into the community and to continue to make this community an amazing place to live.”
Like Steel Valley, Brentwood Borough School District is planning a new elementary school that will be constructed at the Catholic Diocese of Pittsburgh’s former St. Sylvester School, which closed in 2019. The district purchased the school and convent for $200,000 with plans to demolish the current structures and build a new school that will combine students from the district’s two elementary buildings, Elroy and Moore.
The decision to build a new school came as the district saw increasing populations over the past several years. The new school will have capacity for 650 kindergarten through fifth grade students.
The district is now removing asbestos from the old Catholic school before demolition. Work on the new structure is expected to start in the spring.
In all the project could cost between $35 million and $39 million.
Baldwin-Whitehall
In neighboring Baldwin Borough, the Baldwin-Whitehall School District is wrapping up a $49 million elementary school project that will officially welcome third, fourth and fifth graders on Jan. 8.
The R.A. Lutz Elementary School, named for current Superintendent Randal Lutz, takes the place of the former Paynter Elementary School, which was used by the district through March 2020 when it was demolished. Since then crews have been constructing the new school, which will accommodate the district’s growing enrollments.
Bethel Park
Also in Pittsburgh’s South Hills, Bethel Park is undergoing several school construction projects. Renovations are currently ongoing at Independence Middle School, which was constructed in 1975. The goal is to update the building so that it can house sixth, seventh and eighth graders. It is currently used by seventh and eighth graders.
A new elementary school is also being designed, which will bring all of the district’s kindergarten through fifth grade students into the same building rather than being split between five.
The projects came after the district realized in 2020 that all of the Bethel Park school buildings needed “significant investment,” Superintendent James Walsh said Thursday. At the same time, Bethel Park was seeing enrollments begin to steady, meaning they were maintaining buildings that were meant to house more students.
On Thursday, the Independence Middle School was full of children wrapping up their week while construction was ongoing.
Seventh graders are currently using a renovated wing filled with soft colors, open spaces and bright lights. That wing of the building will eventually be used by sixth graders, who are still learning at the Neil Armstrong Middle School, which will eventually be closed. Eighth graders are on the second floor of Independence, which has not yet been renovated. It is filled with small lockers and butternut squash colored walls. At the end of the hall temporary walls have been constructed, behind which workers are renovating a third classroom wing of the school.
That classroom space will be done by December at which point eighth grade students will be transitioned into the newly completed space. Temporary walls will then be constructed around the old wing and work will begin on those classrooms.
The cafeteria will be renovated over the summer as well as a ramp that connects the first and second floors. The ramp, which is not ADA compliant, will be torn down and replaced with an elevator and stairs. Another outside entrance will also be built where the ramp formerly sat.
That project will cost $45 million.
The elementary school will be constructed near the Neil Armstrong Middle School. The school will house kindergarten through fifth graders. Renderings for the new three-story building, which is expected to cost $102 million, show two grades on each floor. The building will feature collaborative spaces where students and teachers can work as well as areas for coding and STEM classes.
School directors are expected to go out to bid next month on the elementary school, with possible approvals in November.
Both projects are slated to be completed in 2026.
South Park
At the neighboring South Park School District work is currently underway on a renovation project at the South Park Elementary Center. The work, which is projected to cost $32 million, will be completed in August 2024.
Overall, construction will create an increase in space for a growing population, dedicated areas for learning support classrooms, speech and language areas, an enhanced technology classroom and large group instruction rooms.
“This is such an exciting and special time for South Park, as we can see our future plans unfolding each day,” Principal Kelli Dellarose said in a statement. “This renovation project will help us to best provide students and staff with the space and resources necessary to continue our educational mission for years to come.”
South Allegheny
In the Mon Valley, the South Allegheny School District began renovating their elementary school this year. Construction is expected to be completed this fall and will create a new Innovation Center for STEM classes, a secure visitor entry to the school, an updated office area and cafeteria and a new overhang at the front of the building, spokeswoman Laura Thomson said.
Hampton Township
In the North Hills, Hampton Township is undergoing a high school renovation. The first phase of work is already completed, featuring a library media center that will allow for interactive teaching and collaborative work. It also features breakout rooms, a technology area, a coffee shop that supports the special education program and small classroom spaces. The first phase, which cost $18.5 million, also consisted of infrastructure work to the parking lots and school roof.
The second phase, which is still being designed, will include an internal redesign of the building to double the size of the musical arts area, redesigning space for technology education and upgrading classrooms to meet the current demands of academic programs. A new entrance will also be constructed.
Hempfield Area
In Westmoreland County, the Hempfield Area School District is working through a high school project that was delayed in August after construction bids came in higher than expected. The project would tear the 66-year-old building down to its structural system and rebuild everything as new. But bids for the first phase of construction totaled $149 million, including a 28% increase in general construction costs, causing school directors to delay the project.
This week officials made some of the first moves on construction in months when they voted to advertise for qualifications for an owner’s representative to help the district navigate the project.
Several other projects are taking place across the region including additions and renovations to Avonworth’s middle and high school, a renovation project at North Hill’s West View Elementary School, a new high school in the Quaker Valley School District and a renovation project at the West Allegheny Middle School.
At Steel Valley, Mr. Sullivan is excited to get the project underway that will provide kids with updated facilities and a space they can be excited to go to each day.
“It’s nice,” Mr. Sullivan said. “It’s a big change. It’s what this district needs.”