The new plan for a science, technology, engineering and math — or STEM — center at Norwin High School would include glassed-in entrances at the north side of the building.

Modular classrooms, already containing heating and air-conditioning ducts and other features, could be built off-site and dropped into interior courtyards.

The details are part of a presentation by Hayes Large Architects LLP Monday on the proposed center.

Original plans called for a $10.6 million free-standing technology center where students would learn the math and technological skills needed for jobs in partnerships with industries.

Advertise with us

Last year, superintendent William Kerr said Bob Carter Cos., the firm helping administrators develop fundraising strategies for the center, said $3.5 million is a realistic fundraising goal for the community.

In response to that, administrators came up with a new $6.5 million plan to add on to the high school while reconfiguring and reusing existing space there.

The internal additions would include computer-assisted drafting labs, a large biomedical lab and an advanced manufacturing center where students could learn specific skills from teachers and representatives from industry.

The cost of the STEM classrooms would be $6,378,000. Other classrooms needed for the district’s new Junior ROTC program, special education and other purposes, would be added at a cost of $4.8 to $5.4 million, Mr. Hudson said.

Architect Dwight Knouse II of Hayes Large said a bond issue would mainly fund the non-STEM rooms in the project.

Advertise with us

District business manager John Wilson gave an overview of how to fund the work.

For the STEM Center, fundraising by Bob Carter Cos. is expected to cover $725,000 in each of the school years from 2014-15 to 2017-18. Fundraising revenue from the school years up through 2019-20 is expected to equal $3.5 million.

If the plan is approved, the district would use $434,000 of its $500,000 Pennsylvania Department of Education STEM grant toward the center during the current school year. According to Mr. Wilson’s notes, the plan also assumes the education department would continue its $500,000 grant each year in the school years 2015-16 through 2018-19.

The district could use a bond issue of either $7.75 million or $9.5 million for the project, Mr. Wilson said. He recommended the $9.5 million bond issue.

At least one school board member was not sold on the project. “We need more information before we can make a decision,” school Director Dennis Rittenhouse said.