Telecommunications company AT&T sued the city of Pittsburgh this week for allegedly failing to process the company’s permit applications and asking for excessive fees for new cell structures.
The suit, brought in federal court on Tuesday, says the city asked for an annual fee of $850 for each cell facility to be built by the company. AT&T claimed the Federal Communications Commission set a “reasonable annual feed” at $270 for such structures.
The city’s fee exceeds the FCC’s fee by “nearly 215%, in violation of federal law,” the lawsuit reads, and officials refused to reduce it before time ran out for the city to act on the applications.
The facilities at issue are "small cells” that usually consist of antennas and related equipment on top of utility poles or other public structures, the lawsuit reads.
AT&T claims in the suit that the city failed to process the applications because the company wouldn’t agree to the allegedly excessive fee. The company claims the city has made an unreasonable delay and effectively prohibited the company from building.
AT&T is asking the court to mandate the city to issue the permits, order the city to stop its “excessive, unreasonable and illegal” fees and award AT&T money to pay the suit’s costs.
A city spokesman said the city does not comment on litigation.
“The city’s lengthy permitting process and excessive fees are inconsistent with federal rules and are barriers for these projects,” said Jim Kimberly, director of AT&T corporate communications. “We remain willing to work with the city, but we had to take this step to move these projects forward.”