Since Shell Chemical announced in June that it would build an ethane cracker plant in Beaver County, municipalities in the region are “aggressively pursuing” business growth, says Mark Scappe, a Moon Transportation Authority board member and a Moon Area school director.

To accommodate new development in Moon, the transportation authority wants to see improvements to the Ewing Road and Cherrington Parkway intersection and a road built to connect Stevenson Mill Road, a dead-end that links to Moon Clinton Road, with University Boulevard near the Port Authority park-n-ride lot.

The $1.29 million of planned improvements to the Ewing/Cherrington intersection would be a collaborative effort with the Allegheny County Airport Authority and include widening Ewing Road, upgrading traffic signals and adding a new access to four development sites.

The new connector road would enable office, industrial, retail and restaurant development in a currently landlocked area reaching as far west at Becks Run Road.

Advertise with us

Opening about 400 acres for development along the proposed Stevenson Mill connector route would be helpful in attracting companies looking for commercial sites near Pittsburgh International Airport, Mr. Scappe said at the June 27 school board meeting.

Costs related to opening of the connection road run between $6.2 million and $6.3 million, said Lynn Colosi, executive director of the transportation authority.

To allow for the intersection upgrades and the new connector road, the Moon Transportation Authority — created in 1986 to provide transportation infrastructure enhancements and economic development opportunities in the township — wants to expand an area called the Thorn Run Transportation District in Moon.

Property taxes on any structures built in the expanded transportation district would be diverted to the transportation authority for 10 years, while taxes on the land value would continue to go to the appropriate taxing authority, Ms. Colosi said. The diverted funds would be used to pay for the proposed projects and for any future transportation projects in the district, she said.

In addition to expanding the size of the transportation district, the authority is asking for an extension of the ordinance covering the tax-abatement revenue allocation program. Currently, it expires in 2021 and the authority wants it extended through April 2026.

Advertise with us

Authority officials presented their proposal to the Moon Area school directors June 27 and gained the school board’s approval July 18. The Moon planning commission has given a favorable review of the plan to township supervisors, who are expected to consider the request after holding a public hearing on the matter on Wednesday.

The authority estimates that 592 temporary construction jobs and more than 2,000 permanent jobs would be created by development of more than 1 million square feet of commercial expansion along the Stevenson Mill connector.

The Ewing/Cherrington intersection upgrade would be completed using a $907,690 grant from the Pennsylvania Department of Transportation with the remaining funds coming from the transportation authority and the airport authority. Transportation authority officials indicated a possibility for 320,000 square feet of office development and 840 permanent employees. If approved, construction there is expected to begin in the fall.

Ms. Colosi said the authority will actively pursue grants to allow the proposed connector project to proceed.

She said the amount of coordination required on a project of this size is “enormous” and would take more than two years to complete.

Advertise with us

David Toal, attorney with the Toal Law Firm and part of the transportation authority team, however, said he would play the part of a “curmudgeon” and estimated the project would be ready for the construction phase in about seven years.

Sonja Reis, freelance writer: suburbanliving@post-gazette.com.