Findlay supervisors have approved two tax-increment financing plans for office parks near Pittsburgh International Airport.
The proposed 20-year TIF districts would involve Findlay, West Allegheny School District and Allegheny County. Over the life of the TIF, 30 percent of the taxes would be paid to the three taxing bodies and 70 percent would pay off development costs.
The school district was expected to vote on the projects this week. The county also must approve the plan before development of the sites can begin.
During initial negotiations, the county’s economic development team requested 75 percent go toward development costs over the length of the TIF, while the township and school district were asking for 60 percent.
If the projects are completed faster than expected, excess funds will be distributed to the taxing bodies. If all taxing parties agree, that money can be used to pay off the special funding earlier.
“We hammered out the best deal that we could get and I am satisfied,” said Janet L. Craig, chairwoman of the supervisors.
The site along McClaren Road will encompass 68 acres located across from the entrance to Industry Drive. Plans include four buildings totaling about 410,000 square feet on the mixed-use site. Planned use is for technology and flexspace.
The second phase of construction at Clinton Commerce Park involves a total of 330 acres, including about 68 acres of undeveloped land originally earmarked for the first phase of construction. Clinton Phase 1, which began in 2004 with building starting in 2005-06, is in full build-out, said Christopher J. Caruso, Findlay manager. The tax abatement will facilitate development of about 990,000 square feet of industrial space, including six building sites with planned uses including a warehouse and distribution and manufacturing.
Private investment at the McClaren site is estimated at $68 million and includes a $5 million state grant. At full build-out, future assessed value of the property is estimated at $46.8 million. Once the TIF is fulfilled, West Allegheny School District should receive about $848,943 annually; Findlay, $73,382; and Allegheny County, about $216,937.
Proposed development at Clinton Phase II is about $60 million and includes a $10 million state grant. When complete, estimated value is $40.89 million. Using current property tax rates, West Allegheny can expect $741,886; Findlay, $64,128; and Allegheny County, $189,580.
Sonja Reis, freelance writer: suburbanliving@post-gazette.com.




Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.