It certainly was not an ostentatious ceremony, but for Crafton officials and residents it was a simple and perfect way to celebrate the long-awaited reopening of Black's Bridge last Thursday.

The two-lane bridge, which carries Crafton Boulevard over the Port Authority West Busway, had been closed for more than 14 months. It opened almost one month earlier that expected.

"I'm ecstatic that the project is done and that the bridge is open," said Council President Ed Stewart, who directed a brief ribbon-cutting ceremony that featured patriotic music played on an old boom box for the council members, borough administrators, members of the public works department and residents who gathered at the bridge.

The bridge closure had been a major concern for many residents and business owners who attended council meetings to complain about the detours and the lack of progress on the project.

Advertise with us

"I felt that we had to have some type of ceremony to mark this event," said Mr. Stewart who noted, "It's like a huge weight has been lifted off of everyone's back."

Mary Rose Louis, secretary at the adjacent Crafton Elementary School, cut a hastily stretched ribbon on one end of the 120-foot-long bridge while Pam Casterline, co-owner of Capretti and Co., a full-service beauty salon, was given the honors at the opposite end. Gail Sakai, wife of local dentist Dr. Charles Sakai, was the first motorist to drive across it.

"It's a shame that it was closed for such a long period of time, but we are very happy that it has opened sooner than expected," said George Werba, co-owner of the salon at 1931 Crafton Blvd. that had been adversely affected by the bridge's closing. With peak retail season approaching, Mr. Werba said that the bridge's opening would bring back customers and improve retail sales.

Borough Manager Doug Sample said that the project was completed by Swank Associated Cos Inc. of New Kensington for $237,000, while inspection services were provided the M. A. Beech Co. of Carnegie for $7,500.

A loan of $500,000 was secured for the project that initially was estimated to cost a minimum of $300,000.

Advertise with us

"It's really an early Christmas gift for the borough," said Mr. Stewart, of the bridge's opening.

The use of a hydro-demolition technique on the old concrete surface necessitated closing the West Busway for four Saturdays.

Mr. Stewart said the use of a special modified latex concrete compound for the bridge surface was expected to extend the life of the bridge for 40 years, instead of the projected 10 to 15 of regular concrete.

To preserve the bridge surface from truck damage, a 5-ton weight limit has been imposed.

The metal structure and walkways will be sandblasted and painted in the spring.