Peters Township Council has voted to prequalify eight contractors for the township’s proposed Rolling Hills Park aquatic center.
The companies that were prequalified to submit bids for the project were: The Albert M. Higley Co.; Nello Construction Co.; Fairchance Construction Co.; P.J. Dick, Inc.; Hudson Group, Inc.; Massaro Corp; Rycon Construction, Inc.; and Mosites Construction Co.
Township manager Paul Lauer pointed out at Monday’s meeting there was a question with regard to Nello Construction being prequalified because of the company’s current situation with the Peters Township School District.
Last month, Nello Construction filed a $7 million lawsuit against the school district for issues regarding work already completed on the new Peters Township High School.
“Having consulted the solicitor, both he and I are of the opinion that a dispute doesn’t necessarily disqualify Nello from being able to be a prequalified contractor on this job,” Mr. Lauer said.
Peters Township received bids earlier this year on the aquatic center project, but those bids were rejected. The lowest bid at that time came in at about $11.5 million.