Mt. Lebanon’s $1.67 million firing range has sat idle for more than a year, but at the July 13 discussion session meeting, commissioners agreed to move forward with the work that would be needed to make the range usable.
The firing range was primarily built for use by Mt. Lebanon’s police department for police training and has sat unusable because noise could be heard outside of the building, specifically in nearby neighborhoods on Cedar Boulevard and Folkstone Drive.
“We know it’s been a long time to get to this point,” said Dan Deiseroth of Gateway Engineers, Mt. Lebanon’s engineering firm.
Mr. Deiseroth and outside sound experts hired by the municipality and in collaboration with the project’s designer, RSSC Architecture of Pine, came to an agreement on how to lessen the sound problem.
“Essentially, what the remediation is coming down to is the construction of what I’ll call a penthouse around a major portion of the mechanical equipment” as well as the installation of silencers around the mechanical equipment itself, Mr. Deiseroth said.
He said the combination of the sound mitigation and the penthouse “will both improve the sound issues that would be heard by residents along Cedar Boulevard and residents on Folkstone.”
Mr. Deiseroth said the penthouse will be “sort of like an appendage that sits on the roof of this one-story building.”
The low bid for the cost of the mitigation is $561,200. Mt. Lebanon has come to an agreement with RSSC Architecture and the firm will pay 34% of the cost of the remediation, or $190,808. Mt. Lebanon would pay 66%, which is $370,392. The funds will come from Mt. Lebanon’s general fund budget set aside for the firing range contingency.
The commissioners could award a contract for the work at their July 27 meeting.
The firing range was part of a 2017 expansion of the municipality’s public works facility. Commissioners approved bids for the firing range construction in June 2018 and a final walk-through of the completed structure was done in June 2019.
At that time, Mt. Lebanon’s then-chief inspector Joe Berkley and members of the Mt. Lebanon Police Department observed firing tests. Sounds were heard in the surrounding neighborhoods.
RSSC Architecture did a sound study in July 2019 and noted that compliance with the 65-decibel design standard was not achieved.
Commissioners also came to a consensus to install ballistic walls in the firing range. The walls, which are made of crushed rubber, are meant to capture any inadvertent rounds that are fired, said police Chief Aaron Lauth.
Chief Lauth said the walls would also make it possible for the police officers to do movement-type drills and not just stationary drills as part of their required training. The cost of the ballistic walls is estimated at $117,000.