Dave Osterhus of West Mifflin knew this day could come when he bought his two-bedroom townhouse on Village Lane eight years ago. But that doesn’t make the reality any easier to handle.

Within the next year, Mr. Osterhus will have to move — his property is in the path of the next segment of construction for the Mon-Fayette Expressway. He doesn’t know when or where he’ll go, because the Pennsylvania Turnpike Commission hasn’t made an offer yet.

“People ask me where I’m looking, and I have to tell them I don’t know yet,” Mr. Osterhus said after reviewing construction plans for the toll road at an open house Tuesday in Pleasant Hills. “Anything you look at now may be gone in three or six months.”

Mr. Osterhus was among dozens of Monongahela Valley residents who reviewed plans and had initial meetings Tuesday with turnpike acquisition officials. The turnpike is refining plans for the $900 million, 8-mile section of the toll road between Route 51 in Jefferson Hills and Route 837 in Duquesne.

Advertise with us

The 43 residences along Village Lane, a cul de sac near the Allegheny County Airport, are among 285 parcels the agency is sure it will take, said Jeanmarie McLaughlin, turnpike assistant counsel who oversees acquisitions. More property acquisitions will be forthcoming over the next five years as final design plans are finalized, she said.

“We’re going to be starting as soon as possible, pretty much as soon as these meetings are done,” Ms. McLaughlin said. “We know some folks who have hardships or are anxious to get moving, and we’ll try to get to them first.”

Several commercial properties, including Begely Welding and the storage yard for Anthony Crane in Duquesne, also will be taken for the project.

Matthew Burda, the turnpike’s project manager, said the agency tries to balance the impact that new construction will have on residences, commercial property and utilities. In this case, one of the major first steps will be relocating three Duquesne Light Co. transmission towers, Mr. Burda said.

“Every project’s different,” he said. “You have to balance it to do what’s right for everybody. Sometimes it’s taking more residential property, sometimes it’s better to move utilities.”

Advertise with us

Mr. Burda said the project likely will be divided into five or six construction contracts, beginning with one to relocate Commonwealth Boulevard near West Mifflin High School and another for a bridge on Route 837 in mid-2021. The project will include 16 bridges and ramps, including bridges added to local roads such as Clairton Road so the new highway can pass beneath them.

This section of the highway is expected to be completed in 2026; none of it will open until all of it is done.

These plans are a revised version that changed the route and reduced the scale of the project. The original concept included a wing to Pittsburgh on the Oakland side of the Monongahela River, but opposition from the city and a prohibitive cost of more than $4 billion delayed the project for about a decade and caused the turnpike to eliminate the Pittsburgh leg.

The first 60 miles of the highway run from West Virginia to Jefferson Hills.

To Mr. Osterhus, the project can’t come soon enough. He has one hope.

Advertise with us

“They make us a good, reasonable offer,” he said. “Houses equal to ours in other neighborhoods cost two-three times as much.

“All we can do is cross our fingers and see what happens.”

The turnpike will repeat the open houses from 6 to 8 p.m. Wednesday and Thursday at Georgetowne Center, 526 East Brucetown Road, Pleasant Hills.

CORRECTION: A previous version of this article incorrectly identified the 8-mile section of the toll road between Route 51 in Jefferson Hills and Route 837 in Duquesne. The article previously had route 52.

Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.