The Upper St. Clair school board on Monday awarded contracts totaling $22.65 million for several capital projects, including a new aquatics center and stadium complex and completion of the field facilities at Boyce Middle School.

Contracts were awarded for general construction, Mucci Construction, $16.15 million; HVAC (heating/ventilation/air conditioning), East West Manufacturing & Supply, $2.46 million; plumbing, Tedesco Plumbing, $1.57 million; and electrical, A-1 Electric, $2.47 million.

Pittsburgh-based PJ Dick serves as construction manager.

The vote was 8-0, with board member Jennifer Bowen abstaining. The decision was greeted with cheers from students as they exited the meeting after the vote.

Advertise with us

The projects include a new aquatics center at the high school with an eight-lane pool and separate special use pool; a new multi-use complex at the stadium that includes district offices; and a single structure at Boyce Middle School with restrooms/changing area, concession area and announcing booth.

The special-use pool will accommodate the district’s swim team and provide for expanded community use and programming. Kept at a warmer temperature, the special use pool can be used for swim lessons for young children and programming for special needs students.

“We will be replacing an aging swimming pool with a new, larger facility that will have greater access and healthier air quality for our students,” Superintendent Patrick O’Toole said.

The district’s central offices, which now are located in the municipal building, will be moved into the new multi-use complex. Stadium seating, restrooms, the press box and concessions area also will be refurbished.

Other components within the construction awards include removal of a pedestrian bridge at the high school; stadium light pole relocations and upgrades; a new stadium scoreboard and sound system; fencing along Washington Road and parking lot paving at the Boyce field site.

Advertise with us

The project’s overall annual budget impact is equal to 0.4576 mills. The estimated tax impact on a home with the median assessed value of $223,550 is $102 annually.

Through a recent bond issuance, the district secured $8.6 million for the project, with another bond issuance expected this year or in 2019.

The plan is to begin construction within the next few weeks. Completion is projected for August 2019.

Margaret Smykla, freelance writer; suburbanliving@post-gazette.com