Construction of two long-planned housing developments at Port Authority rail stations in the South Hills could begin this year.

An authority board committee on Thursday approved a land lease with Dawson Massaro Development Partners for a 300-unit apartment complex next to the South Hills Village parking garage and station. Construction could begin in late July or early August, said Michael Cetra, authority general counsel. The developers expect to have it ready for occupancy in spring 2017.

The partnership will pay the authority $180,000 per year for the 7.1-acre site in the early years of the 50-year lease, with escalation to $590,000 by the end. The developers will have three additional 20-year options on the site. The $46 million project is privately financed.

The committee heard a presentation about a 152-unit apartment building planned for the Castle Shannon park-n-ride lot. Lynn Colosi, consultant to JRA Development Group, said the “best case” scenario has construction on Shannon Village starting Nov. 1 and taking 18 to 24 months.

Advertise with us

Construction is expected to close the park-n-ride lot for about a year, she said. A parking deck will be built next to the eight-story apartment building, providing 541 park-n-ride spaces (34 more than the existing lot) along with 208 spaces for residents and visitors. The building will have studio, one- and two-bedroom units with rents of $1,000 to $1,300 per month. The ground floor will have retail space.

The $42.3 million project includes $12.1 million in public financing from a variety of federal, state and county sources but no Port Authority money.

In other action, an authority board committee approved projects to rehabilitate the Tassey Hollow Bridge on Hawkins Avenue in North Braddock and the Washington Junction park-n-ride lot in Bethel Park.

Work on the bridge will begin in September and October and will detour traffic for a little more than a year, including the 59 Mon Valley and 61A North Braddock bus routes, said Keith Wargo, authority assistant general manager.

The Washington Junction project is expected to start in September and close half of the 294-space lot at a time. Mr. Wargo said the agency hopes to complete the work during this construction season.

Jon Schmitz: jschmitz@post-gazette.com, 412-263-1868 or on Twitter @pgtraffic.