Major traffic pattern changes affecting tens of thousands of drivers are scheduled to occur soon at the Route 51-88 construction site, including the start of a five-month full closure of northbound Route 88.
The around-the-clock closure is scheduled to begin at 7 p.m. June 22, blocking access for traffic headed from Route 88 to Route 51. The closure will occur at Tariff Street, a short side street about 800 feet from the 51-88 intersection in Overbrook. Access to businesses in the area will be maintained.
Also that day, Hillview Street will close to traffic between Route 51 and Kingwood Street for roadway and culvert reconstruction and the staircase along Hillview Street will close. Pedestrian traffic will use a temporary crossing on Route 88. All other traffic will be detoured.
But other changes occurring at the site will make things a bit easier for drivers of the roughly 40,000 vehicles that use the intersection on a typical day.
The dedicated right-turn lane from southbound Route 51 to southbound Route 88 will reopen. It has been closed since last July, causing big backups during peak periods as turning motorists had to stay in the right travel lane.
The detour of northbound Route 88 traffic will allow the Pennsylvania Department of Transportation to adjust the timing of traffic signals to give Route 51 drivers longer green cycles, spokesman Steve Cowan said.
The posted detour for northbound Route 88 traffic is a long one, using Connor Road to Route 19 north to Route 51 at the Liberty Tunnel interchange, a distance of 10 miles. Unofficial shorter options for drivers include McNeilly Road to Pioneer Avenue to reach Route 19 to the tunnels, or Castle Shannon Boulevard to Scott Road to Route 19, each about five miles.
Enterprising drivers may also find ways around the blockage using streets in Brookline.
PennDOT is not posting McNeilly Road as the detour because it is not a state-maintained road, and it is avoiding Castle Shannon Boulevard because of construction that is occurring between its intersections with Scott Road and Route 19, Mr. Cowan said.
Also part of the June 22 changes is the reopening of a section of Glenbury Street that has been closed during replacement of a box culvert.
Mr. Cowan said the contractor on the $19 million project, Joseph B. Fay Co., is working hard to finish it on schedule in November. “Because the paving season ends prior to then, it’s possible they’ll be done with the bulk of the work and come back in April to complete the paving,” he said.
A key feature of the project, which began in 2013, is a jug handle looping around the Rite Aid store that will be used by northbound Route 51 traffic to reach Route 88 and Glenbury. It replaced a short left-turn lane that often was overstacked, causing delays for through traffic.
Other improvements are a northbound left-turn lane on Route 51 at Stewart Avenue, south of the Route 88 intersection, and a second jug handle for southbound traffic via Fairhaven Road and Stewart Avenue.
Southbound drivers on Route 51 who want to reach St. Norbert Church or the residential areas surrounding it will continue to the jug handle rather than turning left at Ivyglen Street. The jug handle will funnel them to the northbound side.
PennDOT expects the reconfiguration to reduce delays and the incidence of rear-end crashes and improve drainage at the site, which has been prone to flash flooding.